Land Compensation Act 1961
1961 c. 33An Act to consolidate the Acquisition of Land (Assessment of Compensation) Act 1919, and certain other enactments relating to the assessment of compensation in respect of compulsory acquisitions of interests in land; to the withdrawal of notices to treat; and to the payment of additional compensation and of allowances in connection with such acquisitions or with certain sales by agreement of interests in land; with corrections and improvements made under the Consolidation of Enactments (Procedure) Act 1949.
Enacted[22nd June 1961] C1C2C3C4C5I1C6C7C8C9C10C11C12C13C14C15C16C17C352C203C225C195C342C66C182C87C349C269C220C123C90C292C158C282C303C223C116C318C229C215C265C186C325C337C114C241C164C226C321C204C299C351C310C270C273C212C181C60C86C145C72C92C106C102C135C324C202C247C83C196C147C336C228C217C300C309C129C168C289C108C286C162C248C271C68C328C160C95C166C267C155C260C185C171C340C150C287C42C62C193C216C117C130C131C315C345C251C280C109C177C254C77C297C153C175C231C306C157C71C43C314C232C252C44C133C311C211C100C61C240C55C144C288C105C81C45C48C222C137C249C355C179C156C237C163C78C173C207C91C307C191C298C134C58C338C107C356C49C169C188C239C348C290C192C350C198C190C97C235C357C180C335C140C333C209C275C183C295C118C70C94C98C52C161C112C152C308C201C362C224
C361C262C99C143C242C170C194C246C263C103C119C88C200C319C210C272C227C268C259C320C174C80C79C126C120C213C330C277C344C85C127C189C341C167C67C291C208C276C266C149C115C316C256C154C279C218C64C141C73C56C93C261C205C111C54C76C221C304C89C327C326C139C274C264C148C347C110C312C96C122C281C305C176C250C159C283C142C53C138C151C244C343C294C230C257C236C197C187C245C121C219C360C51Part I Determination of Questions of Disputed Compensation¶
1 Upper Tribunal to assess compensation in respect of land compulsorily acquired.¶
Where by or under any statute (whether passed before or after the passing of this Act) land is authorised to be acquired compulsorily, any question of disputed compensation and, where any part of the land to be acquired is subject to a lease which comprises land not acquired, any question as to the apportionment of the rent payable under the lease, shall be referred to the Upper Tribunal and shall be determined by the Tribunal in accordance with the following provisions of this Act.F692 Procedures on references under s. 1. ¶
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .F293 Consolidation of proceedings on claims in respect of several interests in the same land.¶
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .C19C75C206C253C214C113C301C165C132C136C331C104C332C329C74C125C233C184C234C47C172C278C353C824 C18 Costs. ¶
4A Making a claim for compensation¶
C20Part II Provisions determining amount of compensation¶
General provisions¶
C21C22C23C255C69C124C302C178C293C57C334C358C238C199C46C339C128C2965 C339 Rules for assessing compensation.¶
Compensation in respect of any compulsory acquisition shall be assessed in accordance with the following rules:C101C285C243C65C3175A Relevant valuation date¶
F596 Disregard of actual or prospective development in certain cases. ¶
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .C3226A No-scheme principle¶
- “blighted land” means land of a description listed in Schedule 13 to the Town and Country Planning Act 1990;
- “relevant valuation date” has the meaning given by section 5A.
6B Lower compensation if other land gains value¶
6C Increased compensation if other land loses value¶
6D Meaning of “scheme” etc.¶
6E Further provisions in relation to relevant transport projects¶
F597 Effect of certain actual or prospective development of adjacent land in same ownership. ¶
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .F598 Subsequent acquisition of adjacent land and acquisition governed by enactment corresponding to s. 7.¶
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .F599 Disregard of depreciation due to prospect of acquisition by authority possessing compulsory purchase powers.¶
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .Special Cases¶
10 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . F2¶
10A F3Expenses of owners not in occupation.¶
Where, in consequence of any compulsory acquisition of land—C25C2611 Land of statutory undertakers. ¶
In relation to compulsory acquisitions of interest in land which has been acquired by statutory undertakers (within the meaning of the Town and Country Planning Act 1971) for the purposes of their undertaking, the provisions of this Act shall have effect subject to the provisions of subsection (5) of section forty-five of that Act (which makes special provision as to the compensation payable in respect of certain acquisitions of land so acquired).C27C28C31312 Outstanding right to compensation for refusal etc. of planning permission. ¶
C258C28413 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . F5¶
Assumptions as to planning permission¶
14 Taking account of actual or prospective planning permission.¶
14A Cases where prospect of planning permission to be ignored¶
F5715 Planning permission to be assumed for acquiring authority's proposals¶
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .F6516 Special assumptions in respect of certain land comprised in development plans.¶
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .Part III Certification by Planning Authorities of Appropriate Alternative Development¶
17 Certificates of appropriate alternative development ¶
18 Appeal to Upper Tribunal against certificate under section 17¶
19 Extension of ss. 17 and 18 to special cases.¶
20 Power to prescribe matters relevant to Part III.¶
The provisions which may be made by a development order shall include provision for regulating the manner in which applications under section seventeen or nineteen of this Act F34 ... are to be made and dealt with F44 ..., and in particular—F6021 Proceedings for challenging validity of decision on appeal under s. 18.¶
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .22 Interpretation of Part III. C31 ¶
F47Part IV Compensation where Permission for Additional Development Granted after Acquisition¶
F47 23 Compensation where planning decision made after acquisition.¶
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .F4724 Provisions as to claims under section 23.¶
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .F4725 Extension to planning permission where no planning decision made.¶
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .F4726 Extension to Crown development.¶
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .F4727 Application of Part IV to certain cases.¶
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .F4728 Regulations for purposes of Part IV.¶
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .F4729 Interpretation of Part IV.¶
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .Part V Miscellaneous and General¶
30 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . F9¶
C34C354C14631 Withdrawal of notices to treat. C33¶
P1C36C63C50C34632 C35 Rate of interest after entry on land. ¶
33 Application of Act to Crown.¶
This Act applies in relation to the acquisition of interests in land (whether compulsorily or by agreement) by government departments, being authorities possessing compulsory purchase powers, as it applies in relation to the acquisition of interests in land by such authorities which are not government departments.34 Special provision as to ecclesiastical property in England.¶
35 Certificates of value.¶
The Upper Tribunal may on the application of any person certify the value of land being sold by him to an authority possessing compulsory purchase powers, and the sale of the land to that authority at the price so certified shall be deemed to be a sale at the best price that can reasonably be obtained.36 Saving for certain statutory purchases of statutory undertakings.¶
37 Local inquiries.¶
The Minister may cause a local inquiry to be held for the purpose of the exercise of any of his functions under this Act; and the provisions of subsections (2) to (5) of section 250 of the M6Local Government Act 1972 (which relate to the giving of evidence at, and defraying the cost of, local inquiries) shall have effect with respect to any such inquiry.38 Services of notices.¶
- “confirming authority” has the same meaning as in Schedule 2A (see paragraph 9 of that Schedule);
- “working day” means a day other than a Saturday, a Sunday, Christmas Day, Good Friday or a bank holiday under the Banking and Financial Dealings Act 1971 in England and Wales.
39 Interpretation.¶
- “acquiring authority”, in relation to an interest in land, means the person or body of persons by whom the interest is, or is proposed to be, acquired;
- “authority possessing compulsory purchase powers”, where it occurs otherwise than in relation to a transaction, means any person or body of persons who could be or have been authorised to acquire an interest in land compulsorily, and, in relation to any transaction, means any person or body of persons who could be or have been so authorised for the purposes for which the transaction is or was effected or a parish council community council or parish meeting on whose behalf district council, county council or county borough council could be or have been so authorised;
- “building” includes any structure or erection and any part of a building as so defined, but does not include plant or machinery comprised in a building;
- “the current development plan”, in relation to any land, means a development plan comprising that land, in the form in which (whether as originally approved or made . . . F14or as for the time being amended) that plan is in force on the date of service of the notice to treat;
- “development” has the meaning assigned to it by section 22 of the M8Town and Country Planning Act 1971, and “develop” shall be construed accordingly;
- “development order” means an order under subsection (1) of section 24 of the Town and Country Planning Act 1971;
- “development plan” has the meaning assigned to it by section five of the M9Town and Country Planning Act 1947, and includes a plan made under subsection (5) of that section;
- “enactment” includes an enactment in any local or private Act of Parliament and an order, rule, regulation, byelaw or scheme made under an Act of Parliament.
- “land” means any corporeal hereditament, including a building as defined by this section, and includes any interest or right in or over land and any right to water;
- “local enactment” means any local or private Act, or an order confirmed by Parliament or brought into operation in accordance with special parliamentary procedure;
- “local planning authority” shall be construed in accordance with Part I of the Town and Country Planning Act 1990;
- “the Minister” means the Secretary of State;
- “outline application” means an application for planning permission subject to subsequent approval on any matters;
- “planning decision” means a decision made on an application under Part III of the Town and Country Planning Act 1971;
- “planning permission” means permission under Part III of the Town and Country Planning Act 1971;
- “special enactment” means a local enactment, or a provision contained in an Act other than a local or private Act, being a local enactment or provision authorising the compulsory acquisition of land specifically identified therein;
- “tenancy” has the same meaning as in the M10Landlord and Tenant Act 1954.
40 C40†Consequential amendments, repeals, and transitional provisions.¶
41 Saving for transactions before commencement of Act.¶
This Act (including the amendments and repeals made by it) shall not have effect in relation to any compulsory acquisition in pursuance of a notice to treat served before the commencement of this Act . . . F22; nor in relation to any sale of an interest in land by agreement in pursuance of a contract made before the commencement of this Act.42 Short title, commencement and extent.¶
SCHEDULES
F85FIRST SCHEDULE ¶
Actual or Prospective Development relevant for purposes of Sections 6 & 7
Sections 6, 7
F85Part I Description of Development¶
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
F85Part II Special Provisions as to New Towns ¶
F85 Part III Special Provisions as to Urban Development Areas¶
SECOND SCHEDULE ¶
. . . F23
Schedule 2A ¶
Additional compensation where section 14A applied
Section 14A(6)
1 Directions for additional compensation¶
- “the statement of commitments” means the statement of commitments submitted in connection with the compulsory purchase order under section 15A(3) of the Acquisition of Land Act 1981 (and if the statement was amended after its submission, means the statement as amended);
- “the initial direction” means the direction referred to in sub-paragraph (1)(b) (and that direction was “confirmed” when the compulsory purchase order was confirmed with the inclusion of the direction);
- “the project land” means the land treated as the project land for the purposes of the statement of commitments;
1A Power to appoint inspector¶
2 Amount of additional compensation¶
3 Time limit for application for direction¶
An application under paragraph 1(2) may not be made after the expiry of the period of 13 years beginning with the date on which the compulsory purchase order became operative.4 Mortgages¶
5 Successors-in-title¶
6 Consequential losses¶
7 Procedure etc¶
8 Regulations¶
9 Interpretation¶
F95THIRD SCHEDULE ¶
Application of Part IV to Certain Cases
F95 Disturbance, severance and injurious affection¶
F95 Increase in value of contiguous or adjacent land¶
F95 Mortgaged land¶
F95 Settled land¶
F95 Interpretation¶
FOURTH SCHEDULE ¶
ENACTMENTS AMENDED
Section 40.
The Town and Country Planning Act, 1944, and that Act as applied by the New Towns Act, 1946¶
The Lands Tribunal Act, 1949¶
FIFTH SCHEDULE F27 ¶
Footnotes
- C1Act applied (with modifications) (18.6.1992) by British Railways (No. 2) Act 1992 (c. xi), s. 35(3).Act applied (with modifications)(29.1.1993) by 1993 c. i, s. 15(3)Act applied (29.3.1993) by 1993 c. iv, s. 22(7)(with s. 22(6))Act restricted (29.3.1993) by 1993 c. iv, s. 37(3)Act applied (with modifications)(27.5.1993) by 1993 c. vii, s. 22(3)Act applied (with modifications)(1.7.1993) by 1993 c. ix, s. 17(3)Act applied (with modifications)(27.7.1993) by 1993 c. xv, s. 30(3)Act modified (10.11.1993) by 1993 c. 28, s. 161(4), Sch. 19 paras.1,2; S.I. 1993/2762, art.3Act applied (10.11.1993) by 1993 c. 28, ss. 169, Sch. 20 Pt. II para. 4(5); S.I. 1993/2762, art.3Act applied (5.11.1993) by 1993 c. 42, s. 5, Sch. 4 para. 3(3)Act applied (31.3.1994) by 1994 c. iv, Pt. II, s. 12(7) (with s. 28)Act excluded (31.3.1994) by 1994 c. iv, Pt. III, s. 23(3) (with s. 28)Act excluded (5.7.1994) by 1994 c. ix, s. 16(3) (with s. 20)Act applied (21.7.1994) by 1994 c. xi, s. 33(3) (with s. 39)Act applied (21.7.1994) by 1994 c. xv, s. 31(3) (with s. 47)Act applied (21.7.1994) by 1994 c. xv, s. 61(3) (with s. 47)Act applied (28.7.1998) by 1998 c. iv, s. 8(2)Act applied (with modifications) (28.7.1998) by 1998 c. iv, s. 10(3)Act applied (1.10.1998) by 1975 c. 70, Sch. 4 Pt. III, para. 5(5) (as inserted by 1998 c. 38, s. 127, Sch. 13 para. 3 (with ss. 39(2), 143(2)); S.I. 1998/2244, art. 4)Act applied (25.11.1998 for specified purposes and otherwise 3.7.2000) by 1998 c. 45, s. 23, Sch. 6 para. 1(5); S.I. 1998/2952, art. 2(2); S.I. 2000/1173, art. 2(2)(c)Act applied (22.3.2001) by 2001 c. ii, s. 7(2)Act modified (30.4.2002) by S.I. 2002/1064, art. 17(3)Act applied (with modifications) (30.4.2002) by S.I. 2002/1065, art. 17(3)Act: Transfer of functions (1.7.1999) (W.) by S.I. 1999/672, art. 2(a), Sch. 1 (with art. 2 paras. (b)-(f))
- C2Act applied (16.3.1992) by Midland Metro (No. 2) Act 1992 (c. viii), s. 14(6).
- C3Act applied (with modifications) (16.3.1992) by Aire and Calder Navigation Act 1992 (c. iv), s. 27(2).
- C4Act applied (with modifications) (16.3.1992) by London Underground Act 1992 (c. iii), s. 25(3).
- C5Act applied (with modifications) (13.2.1992) by British Railways Act 1992 (c. i), s. 28(3).
- I1Act wholly in force at 1.8.1961 see s. 42(2)
- C6Act applied with modifications by Water Resources Act 1963 (c. 38), s. 67(2), Sch. 8 paras. 12—14, Land Commission Act 1967 (c. 1), s. 10(1), Sch. 3 and Development of Rural Wales Act 1976 (c. 75), s. 5(1), Sch. 3 para. 30(1); modified by Local Government, Planning and Land Act 1980 (c. 65), s. 141, Sch. 27 paras. 9, 10; extended by Land Compensation Act 1973 (c. 26), s. 72(5)
- C7Act modified by New Towns Act 1981 (c. 64, SIF 123:3), ss. 14(2), 16(5), Sch. 6 Pt. II, by Compulsory Purchase (Vesting Declarations) Act 1981 (c. 66, SIF 66:1), s. 7(1)(a) and by Acquisition of Land Act 1981 (c. 67, SIF 28:1), s. 4
- C8Act modified by Housing Act 1988 (c. 50, SIF 61), s. 76(5)(6), Sch. 9 Pt. II para. 6, British Railways Act 1989 (c. iii), s. 26(3) and Town and Country Planning Act 1990 (c. 8, SIF 123:1), ss. 28, 54, Sch. 2 Pt. I para. 1(2), Pt. II para. 1(2), Pt. III para. 2
- C9Act applied (with modifications) by Housing Act 1985 (c. 68, SIF 61), s. 578 and Town and Country Planning Act 1990 (c. 8, SIF 123:1), s. 165(3)
- C10Act applied by Housing Act 1985 (c. 68, SIF 61), ss. 295(3), 307, Housing Act 1988 (c. 50, SIF 61), s. 78(2), Sch. 10 Pt. II para. 4(5), Town and Country Planning Act 1990 (c. 8, SIF 123:1), s. 236(5) and Planning (Listed Buildings and Conservation Areas) Act 1990 (c. 9, SIF 123:1), s. 51(5)
- C11Act amended by Local Government Act 1985 (c. 51, SIF 81:1), s. 4, Sch. 1 Pt. I paras. 15(1), 18(2), Town and Country Planning Act 1990 (c. 8, SIF 123:1), ss. 49, 54(1), and amended (prosp.) by ss. 27, 28 of that Act
- C12Act excluded by British Railways (London) Act 1988 (c. xi), s. 19(3) and Planning (Listed Buildings and Conservation Areas) Act 1990 (c. 9, SIF 123:1), s. 50(4)
- C13Act excluded by Heathrow Express Railway Act 1991 (c. vii), s. 33(3)
- C14Act modified by London Underground (Victoria) Act 1991 (c. x), s. 15(3)
- C15Act modified (25.11.1991) by Planning and Compensation Act 1991 (c. 34, SIF 123:1), s. 27, Sch. 4 Pt. I para. 44(9) (with s. 84(5)); S.I. 1991/2728, art. 2
- C16Act modified (28.11.1991) by London Underground (Safety Measures) Act 1991 (c. xviii), s. 20(3).
- C17Act modified (19.12.1991) by London Docklands Railway Act 1991 (c. xxiii), s. 10(3)Act modified (1.4.1996) by 1990 c. 8, Sch. 2 Pt. 1A (as inserted by 1994 c. 19, s. 20(3), Sch. 5 Pt. II, para. 8 (with ss. 54(5)(7), 55(5), Sch. 17 paras. 22(1), 23(2)); S.I. 1995/3198, art. 4, Sch. 2)Act modified (1.4.1996) by 1994 c. 19, s. 20(3), Sch. 5 Pt. III, para. 17(2)(3) (with ss. 54(5)(7), 55(5), Sch. 17 paras. 22(1), 23(2)); S.I. 1995/3198, art. 4, Sch. 2Act modified (25.11.1998 for specified purposes and otherwise 3.7.2000) by 1998 c. 45, s. 19(6)-(8), Sch. 4 paras. 1-5; S.I. 1998/2952, art. 2(2); S.I. 2000/1173, art. 2(2)(c)
- C18S. 4 applied (with modifications) by Acts listed in Chronological Table of the Statutes, Local Government, Planning and Land Act 1980 (c. 65), s. 167(9), National Heritage Act 1983 (c. 47, SIF 3, 78), s. 36(10) and Mineral Workings Act 1985 (c. 12, SIF 86), ss. 7(13), 8(11); applied by Electricity Act 1989 (c. 29, SIF 44:1), ss. 10(1), 112(3), Sch. 4 paras. 7(4), 11(3), Sch. 17 para. 35(1); applied (with modifications) by Water Act 1989 (c. 15, SIF 130), ss. 153(1), 155, Sch. 19 paras. 6(4)(7), 11, Sch. 20 para. 8(6), (with ss. 58(7), 101(1), 141(6), 160(1)(2)(4), 163, 189(4)–(10), 190, 193(1), Sch. 26 paras. 3(1)(2), 17, 40(4), 57(6), 58)
- C19S. 4 applied (with modifications) (1.12.1991) by the Water Industry Act 1991 (c. 56, SIF 130), ss. 167, 180, 223(2), Sch. 11 para. 8(6), Sch. 12 para. 3(1) (with ss. 82(3), 186(1), 222(1), Sch. 14 para. 6)S. 4 applied (with modifications) (1.12.1991) by Water Resources Act 1991 (c. 57, SIF 130), ss. 61 (5), 62(5), 168(3), 177, 225(2), Sch. 7 para. 5, Sch. 19 para. 8(6), Sch. 21 para. 3(1) (with ss. 16(6), 179, 222(3), Sch. 22 para. 1, Sch. 23 para. 6)S. 4 applied (with modifications) (30.10.1994) by S.I. 1994/2716, art. 92(4)S. 4 applied (with modifications) (30.10.1994) by S.I. 1994/2716, reg. 96(3)S. 4 applied (1.6.1997) by S.I. 1997/1160, reg. 14(6)S. 4 applied (with modifications) (1.10.1998) by 1975 c. 70, Sch. 4 Pt. 1V, para. 15(4) (as inserted by 1998 c.38, s. 127, Sch. 13 para. 3 (with ss. 139(2), 143(2)); S.I. 1998/2244, art. 4)S. 4 applied (with modifications) (1.4.1999) by S.I. 1999/481, reg. 8(4)S. 4 applied (with modifications) (29.4.1999) by S.I. 1999/1006, reg. 7, Sch. para. 6S. 4 applied (with modifications) (26.3.2001) by 2000 c. 26, s. 95, Sch. 6 para. 5(2); S.I. 2000/2957, art. 2(3), Sch. 3S. 4 applied (with modifications) (1.4.2000) by S.I. 2000/227, reg. 6, Sch. 2 para. 6(4)S. 4 applied (with modifications) (W.) (1.7.2001) by S.I. 2001/2197, reg. 6, Sch. 2 para. 6(4)
- C20Pt. II (ss. 5-16) applied (with modifications) (16.1.1995) by 1995 c. i, s. 9(3) (with ss. 34, 35)
- C21S. 5 applied (with modifications) by Acts listed in Chronological Table of the Statutes; and s. 5 modified by: Agriculture Act 1967 (c. 22), s. 50(8); Leasehold Reform Act 1967 (c. 88), ss. 29, 30, Sch. 4 para. 3(5); S.I. 1976/1218, art. 4; and Highways Act 1980 (c. 66), s. 261(6)
- C22S. 5 applied (with modifications) by National Heritage Act 1983 (c. 47, SIF 3, 78), s. 36(10), Water Act 1989 (c. 15, SIF 130), s. 155, Sch. 20 para 8(7) (with ss. 58(7), 101(1), 141(6), 160(1)(2)(4), 163, 189(4)–(10), 190, 193(1), Sch. 26 paras. 3(1)(2), 17, 40(4), 57(6), 58), Town and Country Planning Act 1990 (c. 8, SIF 123:1), s. 136(1)(a) and Aviation and Maritime Security Act 1990 (c. 31, SIF 39:2), s. 43(5), Sch. 2 para. 4(a)
- C23S. 5 applied (with modifications) (1.12.1991) by Water Industry Act 1991 (c. 56, SIF 130), ss. 167, 180, 223(2), Sch. 11 para. 8(7), Sch. 12 para. 3(2) (with ss. 82(3), 186(1), 222(1), Sch. 14 para. 6)S. 5 applied (with modifications) (1.12.1991) by Water Resources Act 1991 (c. 57, SIF 130), ss. 61(6), 177, 225(2), Sch. 7 para. 5, Sch. 21 para. 3(2) (with ss. 16(6), 179, 222(3), Sch. 22 para. 1, Sch. 23 para. 6)S. 5 applied (with modifications) (30.10.1994) by S.I. 1994/2716, regs. 91(5), 96(4)S. 5 applied (with modifications) (1.4.1999) by S.I. 1999/481, reg. 7(2)S. 5 applied (29.4.1999) by S.I. 1999/1006, reg. 7, Sch. para. 5S. 5 applied (with modifications) (1.8.2000) by S.I. 2000/1973, reg. 12(13), Sch. 6 para. 6(2)S. 5 applied (1.4.2000) by S.I. 2000/227, reg. 6, Sch. 2 para. 5(2)S. 5 applied (with modifications) (W.) (1.7.2001) by S.I. 2001/2197, reg. 6, Sch. 2 para. 5(2)
- C24S. 5(2)(4) applied (5.11.1993) by 1993 c. 42, s. 21, Sch. 7 para. 16(2)(a)
- F1Words in s. 5(3) repealed (25.9.1991, subject to the restrictions referred to in S.I. 1991/2067, art. 4, Sch. 2 Pt. I para. 4) by Planning and Compensation Act 1991 (c. 34, SIF 28:1), ss. 70(a), 84(6), Sch. 15 Pt. I para. 1, Sch. 19 Pt. III (with s. 84(5)); S.I. 1991/2067, art. 3
- F2S. 10 repealed by Local Government and Housing Act 1989 (c. 42, SIF 81:1), s. 194(4), Sch. 12 Pt. II
- F3S. 10A inserted (25.9.1991, subject to the restrictions referred to in S.I. 1991/2067, art. 4, Sch. 2 Pt. I para. 4) by Planning and Compensation Act 1991 (c. 34, SIF 28:1), s. 70(a), Sch. 15 Pt. I para.2 (with s. 84(5)); S.I. 1991/2067, art.3
- C25S. 11 extended by Post Office Act 1969 (c. 48), Sch. 4 para. 93(1) and by Civil Aviation Act 1982 (c. 16, SIF 9), s. 19(2), Sch. 2 para. 4
- C26S. 11 modified (1.4.2001) by 2000 c. 38, s. 37, Sch. 5 para. 1(2)(g) (with s. 106); S.I. 2001/869, art. 2
- F4Words substituted by virtue of Town and Country Planning Act 1971 (c. 78), Sch. 24 para. 2
- C27References to Town and Country Planning Act 1954 (c. 72), ss. 23, 28(5) and 39 and Pts. II and V to be construed as references to Town and Country Planning Act 1971 (c. 78), ss. 36, 158(5) and 166 and Pt. VIII: ibid., Sch. 24 Pts. I, VII
- C28S. 12 applied (with modifications) (30.10.1994) by S.I. 1994/2716, reg. 97
- M11954 c. 72.
- M21954 c. 72.
- C29Reference to Town and Country Planning Act 1947 (c. 51), s. 22(1) to be construed as reference to Town and Country Planning Act 1971 (c. 78), s. 166: ibid., Sch. 24 para. 2
- M31947 c. 51.
- F5S. 13 repealed by Statute Law (Repeals) Act 1989 (c. 43), s. 1(1), Sch. 1 Pt. VII
- C30S. 19(1) amended by Compulsory Purchase Act 1965 (c. 56), Sch. 7
- F6Words in s. 19(1) substituted (25.9.1991, subject to the restrictions referred to in S.I. 1991/2067, art. 4, Sch. 2 Pt. 2 para. 5(1)) by Planning and Compensation Act 1991 (c. 34, SIF 28:1), s. 70(b), Sch. 15 Pt. 2 para.17 (with s. 84(5)); S.I. 1991/2067, art. 3
- M41845 c. 18.
- F7Words substituted by Community Land Act 1975 (c. 77), Sch. 10 para. 4(3)(5); continued by Local Government, Planning and Land Act 1980 (c. 65), Sch. 33 para. 5(1)(4)(5) in relation to applications, or certificates issued in pursuance of applications, made after 12.12.1975
- C31S. 22 modified by Local Government, Planning and Land Act 1980 (c. 65), s. 141, Sch. 27 paras. 9, 12
- C32S. 22(2) modified by Housing Act 1988 (c. 50, SIF 61), s. 76(5)(6), Sch. 9 Pt. 2 para. 9(a)S. 22(2) modified (10.11.1993) by 1993 c. 28, s. 161(4), Sch. 19 para.4; S.I. 1993/2762, art. 3
- F8S. 22(3) repealed (25.9.1991, subject to the restrictions referred to in S.I. 1991/2067, art. 4, Sch. 2 Pt. 2 paras. 5(1), 7(2)) by Planning and Compensation 1991 (c. 34, SIF 28:1), ss. 70(b), 84(6), Sch. 15 Pt. 2 para. 18, Sch. 19 Pt. 3 (with s. 84(5)); S.I. 1991/2067, art. 3
- F9S. 30 repealed by Land Compensation Act 1973 (c. 26), Sch. 3
- C33S. 31 excluded by Forestry Act 1967 (c. 10), s. 22(5), Agriculture Act 1967 (c. 22), s. 49(7)(ii), Town and Country Planning Act 1971 (c. 78), s. 208, Land Compensation Act 1973 (c. 26), s. 54(4), Compulsory Purchase (Vesting Declarations) Act 1981 (c. 66, SIF 28:1), s. 7(3) and Town and Country Planning Act 1990 (c. 8, SIF 123:1), ss. 139(5), 143(8), 146(6), 147, 167
- C34S. 31 restricted by Housing Act 1985 (c. 68, SIF 61), s. 227(2)
- C35S. 32 applied with modifications by Agriculture (Miscellaneous Provisions) Act 1968 (c. 34), s. 13(3), Sch. 3 paras. 4, 5(a)
- P1S. 32: for previous exercises of this power, see Index to Government Orders.
- C36S. 32 applied (25.9.1991, subject to the restrictions referred to in S.I. 1991/2067, art. 4, Sch. 2 Pt. I) by Land Compensation Act 1973 (c. 26, SIF 28:1), s. 52A(8)(a) (as inserted by Planning and Compensation Act 1991 (c. 34, SIF 28:1), s. 63(2)); S.I. 1991/2067, arts. 3, 4)S. 32 applied (25.9.1995) by S.I. 1995/2248, art. 5(3)
- P2S. 32(1): power exercised (3.12.1991) by S.I.1991/2732.
- M51845 c. 18.
- F10Words substituted by virtue of Local Government Act 1972 (c. 70), s. 272(2)
- M61972 c. 70.
- C37References to registered letter to be construed as including references to letter sent by recorded delivery service: Recorded Delivery Service Act 1962 (c. 27), s. 1(1)(2), Sch. para. 1
- F11Words substituted by virtue of Town and Country Planning Act 1971 (c. 78), Sch. 24 para. 2
- M71971 c. 78.
- C38Definition of “development plan” explained by Town and Country Planning Act 1971 (c. 78), s. 20
- F12Words inserted by S.I. 1976/315, art. 4(4)
- F13Words in definition of“authority possessing compulsory purchase powers”in s. 39(1) substituted (1.4.1996) by 1994 c. 19, s. 66(6), Sch. 16 para. 17 (with ss. 54(5)(7), 55(5), Sch. 17 para. 22(1), 23(2)); S.I. 1996/396, art. 4, Sch. 2
- F14Word repealed by Town and Country Planning Act 1968 (c. 72), Sch. 11
- F15Words substituted by virtue of Town and Country Planning Act 1971 (c. 78), Sch. 24 para. 2
- M81971 c. 78
- M91947 c. 51
- F16Definition of“local planning authority”in s. 39(1) substituted (23.11.1995) by 1995 c. 25, s. 78, Sch. 10 para. 4(2) (with ss. 7(6), 115, 117, Sch. 8 para. 7); S.I. 1995/2950, art. 2(1)
- F17Words substituted by virtue of S.I. 1965/319, art. 2, Sch. 1 Pt. I and 1970/1681, arts. 2, 6(3)
- M101954 c. 56
- C39S. 39(2) modified by Local Government, Planning and Land Act 1980 (c. 65), s. 141, Sch. 27 paras. 9, 13 and by Housing Act 1988 (c. 50, SIF 61), s. 76(5)(6), Sch. 9 Pt. II para. 10S. 39(2) modified (10.11.1993) by 1993 c. 28, s. 161(4), Sch. 19 para. 5; S.I. 1993/2762, art. 3
- M111971 c. 78
- C40Unreliable marginal note
- M121919 c. 57.
- F18S. 40(2)(b) provides for amendments of enactments specified in Sch. 4
- F19S. 40(3) repealed by Statute Law (Repeals) Act 1974 (c. 22), Sch. Pt. XI
- F20Words substituted by virtue of Interpretation Act 1978 (c. 30), s. 25(2)
- M131978 c. 30.
- F21S. 40(5) repealed by Statute Law (Repeals) Act 1989 (c. 43), s. 1(1), Sch. 1 Pt. VII
- F22Words repealed by Statute Law (Repeals) Act 1989 (c. 43), s. 1(1), Sch. 1 Pt. VII
- F23Sch. 2 repealed by Local Government and Housing Act 1989 (c. 42, SIF 81:1), s. 194(2), Sch. 12 Pt. II
- F24Sch. 4 paras. 1–5 repealed by New Towns Act 1965 (c. 59), Sch. 12
- F25Sch. 4 paras. 6, 7 repealed by Acquisition of Land Act 1981 (c. 67, SIF 28:1), Sch. 6 Pt. I
- C41The text of Sch. 4 para. 8 is in the form in which it was originally enacted: it was not reproduced in Statutes in Force and does not reflect any amendments or repeals which may have been made prior to 1.2.1991
- F26Sch. 4 paras. 9, 10 repealed by Housing (Consequential Provisions) Act 1985 (c. 71, SIF 61), s. 3, Sch. 1 Pt. I
- F27Sch. 5 repealed by Statute Law (Repeals) Act 1974 (c. 22), Sch. Pt. XI
- C42Act applied (with modifications) (5.3.2022) by The Norfolk Vanguard Offshore Wind Farm Order 2022 (S.I. 2022/138), art. 1, Sch. 7 para. 3 (with arts. 41, 42, Sch. 16)
- C43Act modified (4.11.2022) by The A47/A11 Thickthorn Junction Development Consent Order 2022 (S.I. 2022/1070), arts. 1, 47 (with arts. 4, 52, Sch. 9 para. 82)
- C44Act applied (with modifications) (7.12.2022) by The A417 Missing Link Development Consent Order 2022 (S.I. 2022/1248), art. 1, Sch. 6 paras. 1, 2 (with art. 4)
- C45Act applied (with modifications) (7.2.2024) by The Drax Power Station Bioenergy with Carbon Capture and Storage Extension Order 2024 (S.I. 2024/70), art. 1, Sch. 9 paras. 1, 3 (with art. 43, Sch. 12 paras. 5, 24)
- C46S. 5 applied (with modifications) (1.1.2018) by The Water Abstraction (Transitional Provisions) Regulations 2017 (S.I. 2017/1047), regs. 1, 12(1) (with reg. 8)
- C47S. 4 applied (with modifications) (2.12.2024) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 216(4), 255(7) (with s. 247); S.I. 2024/1138, reg. 2(g)
- C48Act applied (with modifications) (9.2.2024) by The A12 Chelmsford to A120 Widening Development Consent Order 2024 (S.I. 2024/60), art. 1, Sch. 6 paras. 1, 2 (with arts. 4, 52, Sch. 11 paras. 6, 24, 39(1), 55(1), 84)
- C49Act applied (with modifications) (18.12.2024) by The Network Rail (Leeds to Micklefield Enhancements) Order 2024 (S.I. 2024/1284), art. 1, Sch. 11 paras. 1, 2 (with Sch. 15)
- C50S. 32 applied (30.11.2017) by The Conservation of Habitats and Species Regulations 2017 (S.I. 2017/1012), regs. 1(2), 30(7)
- C51Pt. 1 applied (11.3.2026) by The Fenwick Solar Farm Order 2026 (S.I. 2026/151), arts. 1, 12(5), 14(3), 19(10), 20(5), 24, 29, 30, 31, 39(3), 40(5) (with Sch. 14)
- F28Words in s. 5A(4A) inserted (19.12.2025 for specified purposes, 18.2.2026 for E. in so far as not already in force) by Planning and Infrastructure Act 2025 (c. 34), ss. 109(7)(b), 118(5)(d) (with s. 116); S.I. 2025/1370, regs. 3(1)(c), 4(1)(j)
- C52Act applied (with modifications) (29.12.2025) by The Helios Renewable Energy Project Order 2025 (S.I. 2025/1372), art. 1, Sch. 8 paras. 1, 3 (with Sch. 9)
- F29S. 3 omitted (1.6.2009) by virtue of The Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307), art. 1, Sch. 1 para. 38 (with Sch. 5)
- F30Words in s. 5A(4) inserted (31.1.2024) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 186(7)(a), 255(7) (with s. 247); S.I. 2024/92, reg. 2(m) (with reg. 6(2))
- C53Pt. 1 applied (25.6.2025) by The M5 Junction 10 Development Consent Order 2025 (S.I. 2025/795), arts. 1, 15(5), 16(6), 19(10), 20(6), 26(5), 30(4), 31(6), 32(8), 36(3), 37(4) (with arts. 4, 19(9), 26(6), 30(5), 31(7), 32(9), 43, Sch. 9)
- C54Pt. 1 applied (5.4.2024) by The National Grid (Yorkshire Green Energy Enablement Project) Development Consent Order 2024 (S.I. 2024/393), arts. 1, 14(7), 15(3), 20(10), 21(7), 26(4), 35(4), 36(8), 37(8), 38(8), 39(7), 46(3), 53(5) (with arts. 20(9), 26(5), 35(5), 36(9)(12), 37(9)(12), 38(9)(12)(13), 39(8), 44, Sch. 15)
- C55Act applied (with modifications) (3.8.2023) by The Hornsea Four Offshore Wind Farm Order 2023 (S.I. 2023/800), art. 1, Sch. 7 paras. 1, 3 (with arts. 42, 43, Sch. 9 Pt. 1 para. 4, Sch. 9 Pt. 3 para. 6(1), Sch. 9 Pt. 4 para. 2, Sch. 9 Pt. 9 para. 4) (as amended (31.1.2024) by The Hornsea Four Offshore Wind Farm (Correction) Order 2024 (S.I. 2024/117), art. 1(2), Sch.)
- C56Pt. 1 applied (7.2.2024) by The Drax Power Station Bioenergy with Carbon Capture and Storage Extension Order 2024 (S.I. 2024/70), arts. 1, 12(5), 16(5), 20(4), 24(4), 25(7), 26(7), 31(3), 32(10) (with arts. 20(5), 25(13), 26(8), 32(9), 43, Sch. 12 paras. 5, 24)
- C57S. 5 applied (with modifications) (6.4.2010) by The Environmental Permitting (England and Wales) Regulations 2010 (S.I. 2010/675), reg. 1(1)(b), Sch. 5 para. 6 (with reg. 1(2), Sch. 4)
- C58Act applied (with modifications) (9.10.2024) by The M3 Junction 9 Development Consent Order 2024 (S.I. 2024/752), art. 1, Sch. 6 paras. 1, 2 (with art. 4, Sch. 10) (as amended by S.I. 2024/1020, Sch.)Act applied (with modifications) (25.10.2024) by The Associated British Ports (Immingham Eastern Ro-Ro Terminal) Development Consent Order 2024 (S.I. 2024/1014), art. 1, Sch. 5 paras. 1, 2 (with arts. 36, 40, Sch. 4)
- C59S. 5A(5A) modified (22.12.2017) by The M20 Junction 10a Development Consent Order 2017 (S.I. 2017/1202), art. 1, Sch. 6 para. 2(2) (with arts. 4, 37)
- F31Words in s. 1 substituted (1.6.2009) by The Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307), art. 1, Sch. 1 para. 37(b) (with Sch. 5)
- C60Act applied (with modifications) (2.1.2018) by The Boston Barrier Order 2017 (S.I. 2017/1329), art. 41 (with arts. 55-57, Sch. 8 para. 13)
- C61Act modified (18.7.2023) by The Longfield Solar Farm Order 2023 (S.I. 2023/734), art. 1, Sch. 10 paras. 1, 3 (with art. 19)
- C62Act modified (10.3.2022) by The Thurrock Flexible Generation Plant Development Consent Order 2022 (S.I. 2022/157), art. 1, Sch. 7 para. 2 (with Sch. 8 Pt. 6 para. 19)
- C63S. 32 applied (1.1.2017) by The Environmental Permitting (England and Wales) Regulations 2016 (S.I. 2016/1154), reg. 1(1), Sch. 5 para. 8(1) (with regs. 1(3), 77-79, Sch. 4)
- C64Pt. 1 applied (4.8.2023) by The A303 (Amesbury to Berwick Down) Development Consent Order 2023 (S.I. 2023/834), arts. 1, 10(7), 11(5), 14(11), 15(6), 17(3), 23(4), 28(4), 29(6), 30(7) (with arts. 6(2), 18, 23(5), 28(5), 29(7), 30(8), 32, Sch. 11 paras. 5, 30)
- C65S. 5A applied (with modifications) (11.2.2021) by High Speed Rail (West Midlands - Crewe) Act 2021 (c. 2), s. 64(1), Sch. 9 paras. 1, 2(9)
- C66Act modified (18.9.2009) by London Underground (Victoria Station Upgrade) Order 2009 (S.I. 2009/2364), art. 27
- C67Pt. 1 applied (4.11.2022) by The A47/A11 Thickthorn Junction Development Consent Order 2022 (S.I. 2022/1070), arts. 1, 16(5), 17(6), 22(10), 23(5), 29(5), 33(4), 34(6), 35(8), 39(3), 40(4) (with arts. 4, 29(6), 33(5), 34(7), 35(9), 37, 52, Sch. 9 para. 82)
- F32S. 18(2A)(2B) inserted (31.1.2025) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 189(4)(b), 255(7) (with s. 247); S.I. 2024/92, reg. 5 (with reg. 6(3)-(5))
- C68Act modified (19.6.2020) by The Cleve Hill Solar Park Order 2020 (S.I. 2020/547), art. 1, Sch. 6 para. 3 (with art. 37)
- F33Words in s. 6D(4)(a) substituted (31.1.2024) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 188(1)(b), 255(7) (with s. 247); S.I. 2024/92, reg. 2(o)
- F34Words in s. 20 repealed (6.4.2012) by Localism Act 2011 (c. 20), ss. 232(4)(a)(i), 240(2), Sch. 25 Pt. 34 (with s. 232(8)); S.I. 2012/628, art. 8(d)(e) (with arts. 9, 12, 13, 16, 18-20) (as amended (3.8.2012) by S.I. 2012/2029, arts. 2, 4)
- F35Words in s. 20(a) substituted (31.1.2025) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 189(6), 255(7) (with s. 247); S.I. 2024/92, reg. 5 (with reg. 6(3)-(5))
- F36Words in s. 31(3) substituted (1.6.2009) by The Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307), art. 1, Sch. 1 para. 43 (with Sch. 5)
- C69S. 5 applied (with modifications) (4.8.2006) by Contaminated Land (England) Regulations 2006 (S.I. 2006/1380), reg. 1(1), Sch. 2 para. 5(2)
- C70Act applied (with modifications) (5.11.2025) by The Tillbridge Solar Order 2025 (S.I. 2025/1105), art. 1, Sch. 10 paras. 1, 3 (with art. 49, Sch. 15)
- C71Act applied (with modifications) (4.11.2022) by The A47/A11 Thickthorn Junction Development Consent Order 2022 (S.I. 2022/1070), art. 1, Sch. 6 paras. 1, 2 (with arts. 4, 52, Sch. 9 para. 82)
- F37S. 18(4) inserted (31.1.2025) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 189(4)(d), 255(7) (with s. 247); S.I. 2024/92, reg. 5 (with reg. 6(3)-(5))
- F38Words in s. 1 heading substituted (1.6.2009) by The Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307), art. 1, Sch. 1 para. 37(a) (with Sch. 5)
- C72Act modified (31.5.2018) by The Silvertown Tunnel Order 2018 (S.I. 2018/574), Sch. 5 para. 2
- C73Pt. 1 applied (11.10.2023) by The Awel y Môr Offshore Wind Farm Order 2023 (S.I. 2023/1033), arts. 1, 11(4), 12(5), 15(5), 16(10), 22(4), 26(4), 27(6), 28(7), 33(3), 34(5)
- C74S. 4 applied (30.11.2017) by The Conservation of Habitats and Species Regulations 2017 (S.I. 2017/1012), regs. 1(2), 30(8)(b)
- C75S. 4 applied (with modifications) (W.) (10.12.2006) by The Contaminated Land (Wales) Regulations 2006 (S.I. 2006/2989), reg. 1(1), Sch. 2 para. 6(4)
- C76Pt. 1 applied (11.4.2024) by The HyNet Carbon Dioxide Pipeline Order 2024 (S.I. 2024/436), arts. 1(2), 13(4), 15(6), 18(3), 22(7), 23(10), 29(4), 33(4), 34(6), 35(7), 39(3), 40(4) (with arts. 21, 29(5), 33(5), 34(7), 35(8), 41, Sch. 10)
- C77Act applied (2.9.2022) by The A47 North Tuddenham to Easton Development Consent Order 2022 (S.I. 2022/911), arts. 1, 46(3) (with arts. 4, 53)
- F39Words in s. 4(1) substituted (1.6.2009) by The Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307), art. 1, Sch. 1 para. 39(b) (with Sch. 5)
- C78Act applied (with modifications) (13.6.2024) by The Network Rail (Cambridge Re-Signalling) Order 2024 (S.I. 2024/724), art. 1, Sch. 5 paras. 1, 2 (with art. 13)
- F40S. 5A(5B) inserted (3.2.2017) by Housing and Planning Act 2016 (c. 22), s. 216(3), Sch. 18 para. 9; S.I. 2017/75, reg. 3(k)
- C79Pt. 1 applied (2.6.2022) by The M25 Junction 10/A3 Wisley Interchange Development Consent Order 2022 (S.I. 2022/549), arts. 1, 14(5), 15(7), 20(11), 21(5), 27(5), 31(4), 32(6), 33(7), 39(3), 40(4) (with arts. 6, 20(9), 27(6), 31(5), 32(8), 34, 36)
- C80Pt. 1 applied (12.5.2022) by The M54 to M6 Link Road Development Consent Order 2022 (S.I. 2022/475), arts. 1, 12(5), 13(8), 18(10), 19(5), 24(5), 28(4), 29(6), 30(7), 34(3), 35(4) (with art. 28(5))
- C81Act: power to amend conferred (26.12.2023) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 132, 255(3)(a) (with s. 247)
- C82S. 4 applied (with modifications) (16.3.2026) by Infrastructure (Wales) Act 2024 (asc 3), s. 147(2), Sch. 2 para. 10 (with s. 84(5)); S.I. 2025/1306, art. 2(h)
- C83Act modified (13.3.2019) by The Port of Tilbury (Expansion) Order 2019 (S.I. 2019/359), art. 39(3) (with arts. 55, 56)
- C84S. 4(4)-(6) applied (with modifications) by 1985 c. 68, s. 584B(6) (as substituted (6.4.2006 for E., 16.6.2006 for W.) by Housing Act 2004 (c. 34), s. 270(4)(5)(f), Sch. 15 para. 31; S.I. 2006/1060, art. 2(1)(d) (with Sch.); S.I. 2006/1535, art. 2(b) (with Sch.))
- C85Pt. 1 applied (11.8.2022) by The Sizewell C (Nuclear Generating Station) Order 2022 (S.I. 2022/853), arts. 1, 16(8), 18(6), 19(9), 20(3), 26(10), 33(4), 38(4)(5), 39(6), 41(8)(9), 48(3)(4), 81(7) (with arts. 62, 76, 87, Sch. 19 paras. 4, 78)
- C86Act modified (4.1.2018) by The Blackpool Tramway (Blackpool North Extension) Order 2017 (S.I. 2017/1214), Sch. 4 para. 2 (with arts. 58, 59)
- C87Act modified (20.7.2010) by The Network Rail (Nuneaton North Chord) Order 2010 (S.I. 2010/1721), art. 22
- F41Words in s. 18(3) substituted (31.1.2025) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 189(4)(c), 255(7) (with s. 247); S.I. 2024/92, reg. 5 (with reg. 6(3)-(5))
- F42Words in s. 34(2) inserted (E.) (1.10.2006) by Church of England (Miscellaneous Provisions) Measure 2006 (No. 1), s. 16(2), Sch. 5 para. 8(b); 2006 No. 2, Instrument made by Archbishops
- C88Pt. 1 applied (1.9.2021) by The Network Rail (Teddington Station Access for All) Order 2021 (S.I. 2021/937), arts. 1, 10(4), 11(6), 14(4), 16(14), 19(3), 20(6) (with arts. 10(5), 11(7), 14(5))
- C89Pt. 1 applied (13.6.2024) by The Network Rail (Cambridge Re-Signalling) Order 2024 (S.I. 2024/724), arts. 1, 3(3), 8(6), 9(6), 11(6) (with arts. 3(4), 13, Sch. 6)
- C90Act modified (12.8.2012) by The Hinkley Point (Temporary Jetty) (Land Acquisition) Order 2012 (S.I. 2012/1924), art. 8
- C91Act applied (with modifications) (3.8.2024) by The Mallard Pass Solar Farm Order 2024 (S.I. 2024/796), art. 1, Sch. 10 paras. 1, 3 (with Sch. 15)
- C92Act modified (4.6.2018) by The Network Rail (Kings Mill No. 1 Level Crossing) (Land Acquisition and Closure) Order 2018 (S.I. 2018/571), art. 12
- C93Pt. 1 applied (9.2.2024) by The A12 Chelmsford to A120 Widening Development Consent Order 2024 (S.I. 2024/60), arts. 1, 18(5), 19(6), 25(11), 26(5), 31(5), 34(3), 39(4), 40(6), 41(9), 46(3), 47(11), 53(3), 56(4) (with arts. 4, 25(9), 31(6), 40(8), 41(10), 52, Sch. 11 paras. 6, 24, 39(1), 55(1), 84)
- C94Act applied (with modifications) (13.11.2025) by The Stonestreet Green Solar Order 2025 (S.I. 2025/1175), art. 1, Sch. 11 paras. 1, 3 (with art. 40, Sch. 13)
- F43Words in s. 6E(2)(a) substituted (31.1.2024) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 188(2)(a), 255(7) (with s. 247); S.I. 2024/92, reg. 2(o)
- C95Act modified (29.10.2020) by The Southampton to London Pipeline Development Consent Order 2020 (S.I. 2020/1099), Sch. 6 para. 2 (with art. 302, Sch. 9 para. 36)
- C96Pt. 1 applied (17.2.2025) by The Heckington Fen Solar Park Order 2025 (S.I. 2025/85), arts. 1, 11(3), 15(10), 16(6), 20(4), 25(5), 26(7), 27(7), 35(3), 36(4) (with arts. 20(5), 26(8)(11), 27(8), 43, Sch. 13)
- F44Word in s. 20 repealed (6.4.2012) by Localism Act 2011 (c. 20), ss. 232(4)(a)(ii), 240(2), Sch. 25 Pt. 34 (with s. 232(8)); S.I. 2012/628, art. 8(d)(e) (with arts. 9, 12, 13, 16, 18-20) (as amended (3.8.2012) by S.I. 2012/2029, arts. 2, 4)
- C97Act applied (with modifications) (24.4.2025) by The London Luton Airport Expansion Development Consent Order 2025 (S.I. 2025/463), art. 1, Sch. 6 paras. 1, 3 (with art. 39, Sch. 8)
- C98Act applied (with modifications) (27.11.2025) by The Cory Decarbonisation Project Order 2025 (S.I. 2025/1227), art. 1, Sch. 9 paras. 1, 3 (with Sch. 12)
- C99Pt. 1 applied (31.12.2020) by The Network Rail (Cambridgeshire Level Crossing Reduction) Order 2020 (S.I. 2020/1485), arts. 1, 9(4), 10(6), 14(4), 15(4), 18(15), 23(6), 24(7), 26(5), 27(4), 32(3)
- C100Act modified (10.3.2023) by The A47 Wansford to Sutton Development Consent Order 2023 (S.I. 2023/218), arts. 1, 45 (with arts. 4, 50)
- F45S. 5A(6)(b) omitted (13.7.2016) by virtue of Housing and Planning Act 2016 (c. 22), s. 216(3), Sch. 16 para. 1(a); S.I. 2016/733, reg. 3(j)
- C101S. 5A modified (30.4.2015) by Energy Act 2013 (c. 32), ss. 124(6)(a), 156(1) (with s. 130); S.I. 2015/817, art. 2(a)
- F46Words in s. 17(10) omitted (31.1.2025) by virtue of Levelling-up and Regeneration Act 2023 (c. 55), ss. 189(3)(e)(ii), 255(7) (with s. 247); S.I. 2024/92, reg. 5 (with reg. 6(3)-(5))
- C102Act modified (24.8.2018) by The Network Rail (Werrington Grade Separation) Order 2018 (S.I. 2018/923), Sch. 9 para. 2 (with art. 31(2))
- C103Pt. 1 applied (1.4.2021) by The Network Rail (Ferryboat Lane Footbridge Reconstruction) (Land Acquisition) Order 2021 (S.I. 2021/299), arts. 1, 6(6), 7(6), 9(2) (with art. 11)
- C104S. 4 applied (with modifications) (E.) (19.7.2015) by The Environmental Damage (Prevention and Remediation) (England) Regulations 2015 (S.I. 2015/810), reg. 1(1), Sch. 6 para. 7(2) (with regs. 4-8)
- C105Act applied (with modifications) (11.10.2023) by The Awel y Môr Offshore Wind Farm Order 2023 (S.I. 2023/1033), art. 1, Sch. 8 paras. 1, 2
- C106Act modified (28.6.2018) by The High Speed Rail (London West Midlands) (Greatmoor Railway Sidings Etc.) Order 2018 (S.I. 2018/693), art. 12(3)
- C107Act applied (W.) (4.11.2024) by Historic Environment (Wales) Act 2023 (asc 3), ss. 142(5), 212(2) (with Sch. 14 paras. 1-3); S.I. 2024/860, art. 3(b)
- F47Pt. IV omitted (22.9.2017) by virtue of Neighbourhood Planning Act 2017 (c. 20), ss. 33(1)(a), 46(1); S.I. 2017/936, reg. 3(c)
- C108Act modified (1.5.2020) by The Riverside Energy Park Order 2020 (S.I. 2020/419), Sch. 8 para. 3 (with art. 7)
- C109Act applied (with modifications) (2.8.2022) by The Network Rail (Oxford Station Phase 2 Improvements (Land Only)) Order 2022 (S.I. 2022/871), art. 1, 11(3), Sch. 1 paras. 1, 2 (with art. 11(1)(2))
- C110Pt. 1 applied (18.12.2024) by The Network Rail (Leeds to Micklefield Enhancements) Order 2024 (S.I. 2024/1284), arts. 1, 10(6), 12(6), 17(9), 18(3), 20(10), 21(15), 27(3), 28(6), 29(7), 30(5), 32(5), 37(3), 45(3) (with arts. 21(16), 27(5), 28(7), 29(8), 32(6), Sch. 15)
- C111Pt. 1 applied (28.3.2024) by The A66 Northern Trans-Pennine Development Consent Order 2024 (S.I. 2024/360), arts. 1, 10(6), 11(5), 14(11), 15(6), 17(5), 23(4), 28(4), 29(6), 30(7) (with arts. 18, 23(5), 28(5), 29(7), 30(8), 35, Sch. 9)
- C112Act applied (with modifications) (18.2.2026) by Planning and Infrastructure Act 2025 (c. 34), s. 118(3), Sch. 4 paras. 17, 18 (with s. 116); S.I. 2025/1370, reg. 4(1)(l)
- C113S. 4 modified (1.4.2010) by The Conservation of Habitats and Species Regulations 2010 (S.I. 2010/490), regs. 1(2), 32(3) (with reg. 125)
- C114Act modified (30.9.2015) by The Network Rail (Blackthorn and Piddington) (Land Acquisition) Order 2015 (S.I. 2015/1684), art. 9(3)
- F48S. 18(2)(aa) inserted (31.1.2025) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 189(4)(a)(i), 255(7) (with s. 247); S.I. 2024/92, reg. 5 (with reg. 6(3)-(5))
- C115Pt. 1 applied (13.2.2023) by The East Northamptonshire Resource Management Facility Order 2023 (S.I. 2023/110), arts. 1, 12(5), 13(3) (with art. 9)
- C116Act modified (9.1.2014) by The Ashton Vale to Temple Meads and Bristol City Centre Rapid Transit Order 2013 (S.I. 2013/3244), art. 31 (with arts. 57, 58, Sch. 11 para. 19)
- C117Act applied (with modifications) (22.4.2022) by The East Anglia ONE North Offshore Wind Farm Order 2022 (S.I. 2022/432), art. 1(2), Sch. 8 para. 3 (with arts. 40, 41)
- C118Act applied (with modifications) (22.10.2025) by The A46 Newark Bypass Development Consent Order 2025 (S.I. 2025/1090), art. 1, Sch. 6 paras. 1, 2 (with arts. 4, 9, 51, Sch. 9)
- C119Pt. 1 applied (16.4.2021) by The Network Rail (Chart Leacon) Order 2021 (S.I. 2021/419), arts. 1, 8(7), 11(5), 13(3), 14(15) (with art. 11(6), Sch. 5 Pt. 2)
- C120Pt. 1 applied (30.6.2022) by The Network Rail (Essex and Others Level Crossing Reduction) Order 2022 (S.I. 2022/651), arts. 1, 9(6), 13(4), 14(3), 17(13), 21(6), 22(7), 24(5), 25(4), 30(3) (with arts. 14(4), 21(7), 22(8), 24(6))
- C121Pt. 1 applied (25.2.2026) by The A46 Coventry Junctions (Walsgrave) Development Consent Order 2026 (S.I. 2026/125), arts. 1, 15(5), 16(3), 17(4), 22(11), 23(6), 24(3), 25(4), 30(5), 37, 38, 39 (with arts. 40, 45, Sch. 9)
- C122Pt. 1 applied (27.2.2025) by The Associated British Ports (Immingham Green Energy Terminal) Order 2025 (S.I. 2025/165), arts. 1, 11(5), 13(8), 14(3), 19(7), 20(11), 26(6), 28(4), 31(8), 32(7), 53(3), 54(5) (with arts. 20(9)(13), 26(7), 28(5), 31(9)(12), 32(8), 48, 59, Sch. 14)
- F49S. 31(3A) inserted (6.4.2018) by Housing and Planning Act 2016 (c. 22), ss. 193(2), 216(3); S.I. 2018/251, reg. 4(d) (with reg. 6)
- F50S. 17(3)(ba) substituted for s. 17(3)(a)(b) (31.1.2025) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 189(3)(c), 255(7) (with s. 247); S.I. 2024/92, reg. 5 (with reg. 6(3)-(5))
- F51Words in s. 14(9) substituted (31.1.2025) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 189(2)(d), 255(7) (with s. 247); S.I. 2024/92, reg. 5 (with reg. 6(3)-(5))
- C123Act modified (7.8.2012) by The Ipswich Barrier Order 2012 (S.I. 2012/1867), art. 30(4) (with arts. 46-48, Sch. 8 para. 18)
- C124S. 5 applied (with modifications) (10.12.2006) by The Contaminated Land (Wales) Regulations 2006 (S.I. 2006/2989), reg. 1(1), Sch. 2 para. 5(2)
- C125S. 4 modified (30.11.2017) by The Conservation of Habitats and Species Regulations 2017 (S.I. 2017/1012), regs. 1(2), 34(3)
- C126Pt. 1 applied (6.6.2022) by The M25 Junction 28 Development Consent Order 2022 (S.I. 2022/573), arts. 1, 13(5), 14(3), 15(4), 21(11), 22(5), 23(3), 24(4), 29(5), 33(4), 34(6), 35(9) (with arts. 5, 21(9), 33(5), 34(8)(11), 35(10), 36, 38)
- C127Pt. 1 applied (2.9.2022) by The A47 North Tuddenham to Easton Development Consent Order 2022 (S.I. 2022/911), arts. 1, 15(5), 16(6), 21(10), 22(5), 28(5), 32(4), 33(6), 34(8), 39(3), 40(4) (with arts. 4, 28(6), 32(5), 33(7), 34(9), 53)
- C128S. 5 applied (with modifications) (4.11.2024) by Historic Environment (Wales) Act 2023 (asc 3), ss. 204(1), 212(2) (with Sch. 14 paras. 1-3); S.I. 2024/860, art. 3(c)
- F52S. 5A(4A) inserted (31.1.2024) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 186(7)(b), 255(7) (with s. 247); S.I. 2024/92, reg. 2(m) (with reg. 6(2))
- C129Act modified (4.3.2020) by The Midland Metro (Birmingham Eastside Extension) Order 2020 (S.I. 2020/141), art. 37(3) (with arts. 47, 48, Sch. 10 para. 19)
- C130Act modified (12.5.2022) by The M54 to M6 Link Road Development Consent Order 2022 (S.I. 2022/475), art. 1, Sch. 6 para. 2
- C131Act applied (with modifications) (2.6.2022) by The M25 Junction 10/A3 Wisley Interchange Development Consent Order 2022 (S.I. 2022/549), art. 1, Sch. 6 para. 2 (with arts. 6, 34)
- C132S. 4 applied (with modifications) (E.) (6.4.2012) by The Town and Country Planning (Tree Preservation)(England) Regulations 2012 (S.I. 2012/605), regs. 1(1), 24(9) (with reg. 24(10))
- C133Act modified (29.12.2022) by The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022 (S.I. 2022/1396), art. 1, Sch. 7 para. 3 (with art. 32, Sch. 10 paras. 26(2), 68)
- C134Act applied (with modifications) (4.10.2024) by The National Grid (Bramford to Twinstead Reinforcement) Order 2024 (S.I. 2024/958), art. 1, Sch. 9 paras. 1, 3 (with art. 40, Sch. 14)
- C135Act modified (26.9.2018) by The Network Rail (Felixstowe Branch Line Improvements Level Crossings Closure) Order 2018 (S.I. 2018/937), art. 16
- C136S. 4 modified by S.I. 2006/1380, Sch. 2 para. 6(4) (as substituted (6.4.2012) by The Contaminated Land (England) (Amendment) Regulations 2012 (S.I. 2012/263), regs. 1, 2(4))
- C137Act applied (with modifications) (13.3.2024) by The Medworth Energy from Waste Combined Heat and Power Facility Order 2024 (S.I. 2024/230), art. 1, Sch. 9 paras. 1, 3 (with Sch. 11 paras. 5, 22, 37, 47, 82, 110)
- F53Words in s. 5A(4A) inserted (19.12.2025 for specified purposes, 18.2.2026 for E. in so far as not already in force) by Planning and Infrastructure Act 2025 (c. 34), ss. 109(7)(a), 118(5)(d) (with s. 116); S.I. 2025/1370, regs. 3(1)(c), 4(1)(j)
- C138Pt. 1 applied (11.7.2025) by The Oaklands Farm Solar Park Order 2025 (S.I. 2025/739), arts. 1, 11(6), 15(10), 16(5), 20(4), 25(4), 26(7), 27(7), 36(3), 37(4) (with arts. 15(9), 20(5), 25(5), 26(8)(11)(13), 27(8), Sch. 10)
- C139Pt. 1 applied (3.8.2024) by The Mallard Pass Solar Farm Order 2024 (S.I. 2024/796), arts. 1, 11(5), 12(7), 17(10), 18(6), 23(4), 28(4), 29(7), 30(7), 38(3) (with arts. 17(9), 23(5), 28(5), 29(8)(11)(13), 30(8), 32, Sch. 15)
- C140Act applied (with modifications) (11.7.2025) by The Oaklands Farm Solar Park Order 2025 (S.I. 2025/739), art. 1, Sch. 7 paras. 1, 3 (with Sch. 10)
- C141Pt. 1 applied (7.9.2023) by The A38 Derby Junctions Development Consent Order 2023 (S.I. 2023/923), arts. 1, 15(5), 16(6), 21(10), 22(5), 28(5), 32(4), 33(7), 34(8), 39(3), 40(4) (with arts. 4, 21(9), 28(6), 32(5), 33(8), 34(9), 36, 45, Sch. 9 paras. 6, 46, 54(1))
- C142Pt. 1 applied (31.5.2025) by The East Yorkshire Solar Farm Order 2025 (S.I. 2025/585), arts. 1, 11(5), 12(3), 18(10), 19(5), 23(4), 28(4), 29(7), 30(7), 38(3), 39(5) (with arts. 18(9), 23(5), 28(5), 29(8)(11)(13), 30(8), 49, Sch. 14)
- C143Pt. 1 applied (19.1.2021) by The Network Rail (Suffolk Level Crossing Reduction) Order 2020 (S.I. 2020/1663), arts. 1, 9(6), 13(4), 14(3), 18(14), 22(6), 23(7), 25(2), 28(3) (with arts. 22(7), 23(8), 25(3))
- C144Act applied (with modifications) (4.8.2023) by The A303 (Amesbury to Berwick Down) Development Consent Order 2023 (S.I. 2023/834), arts. 1, 36, Sch. 5 paras. 1, 2 (with arts. 6(2), 18, Sch. 11 paras. 5, 30)
- C145Act applied (18.4.2018) by The Network Rail (Hope Valley Capacity) Order 2018 (S.I. 2018/446), art. 28(5) (with arts. 24(8), 28(6), 33(2))
- C146S. 31 excluded (E.W.) (4.11.2024) by Historic Environment (Wales) Act 2023 (asc 3), s. 212(2), Sch. 9 para. 4(7) (with Sch. 14 paras. 1-3, 11); S.I. 2024/860, art. 3(d)
- C147Act applied (with modifications) (7.5.2019) by The Midland Metro (Birmingham City Centre Extension, etc.) (Edgbaston Extension Land Acquisition) Order 2019 (S.I. 2019/882), arts. 1, 7, Sch. 2 para. 2 (with arts. 12, 18)
- C148Pt. 1 applied (4.10.2024) by The National Grid (Bramford to Twinstead Reinforcement) Order 2024 (S.I. 2024/958), arts. 1, 15(8), 20(11), 21(7), 24(5), 25(8), 26(8), 27(7), 28(4), 36(5), 47(3), 48(5), 49(4) (with arts. 20(9), 24(6), 25(9)(12), 26(9)(12), 27(8), 28(5), 36(6), 40, Sch. 14)
- C149Pt. 1 applied (11.1.2023) by The Network Rail (Cambridge South Infrastructure Enhancements) Order 2022 (S.I. 2022/1406), arts. 1, 8(4), 11(6), 14(3), 17(10), 24(4), 25(6), 26(7), 27(5), 29(5), 33(3) (with arts. 24(5), 25(7), 26(8), 29(6), 34(2), Sch. 12 paras. 5, 47, 79)
- C150Act modified (22.12.2021) by The Morlais Demonstration Zone Order 2021 (S.I. 2021/1478), arts. 1, 33, Sch. 7 para. 2 (with arts. 15, 50, Sch. 11 para. 29)
- C151Pt. 1 applied (28.7.2025) by The Mona Offshore Wind Farm Order 2025 (S.I. 2025/870), arts. 1, 12(6), 17(5), 18(10), 23(4), 27(4), 28(6), 29(7), 34(3), 35(5) (with arts. 18(9), 23(5), 27(5), 28(7), 29(8), 37, 38, Sch. 10)
- C152Act applied (with modifications) (25.2.2026) by The A46 Coventry Junctions (Walsgrave) Development Consent Order 2026 (S.I. 2026/125), art. 1, Sch. 7 paras. 1, 2 (with arts. 40, 45, Sch. 9)
- C153Act modified (8.9.2022) by The Manston Airport Development Consent Order 2022 (S.I. 2022/922), art. 1, Sch. 6 paras. 1, 2 (with arts. 5, 40)
- F54S. 14(2)(b) substituted (31.1.2025) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 189(2)(a), 255(7) (with s. 247); S.I. 2024/92, reg. 5 (with reg. 6(3)-(5))
- C154Pt. 1 applied (27.7.2023) by The Boston Alternative Energy Facility Order 2023 (S.I. 2023/778), arts. 1, 13(6), 14(3), 16(3), 19(4), 21(5), 22(10), 23(3), 28(4), 33(7), 34(8) (with arts. 5, 22(9), 28(5), 33(9)(13), 34(9), 36, 53, Sch. 8 paras. 6, 64)
- C155Act applied (22.1.2021) by The Hornsea Three Offshore Wind Farm Order 2020 (S.I. 2020/1656), arts. 1, 17(5) (with arts. 40, 41, Sch. 9 Pt. 5 para. 18)
- C156Act applied (with modifications) (11.4.2024) by The HyNet Carbon Dioxide Pipeline Order 2024 (S.I. 2024/436), art. 1(2), Sch. 9 paras. 1, 2 (with arts. 21, 41, Sch. 10)
- C157Act modified (3.11.2022) by The Network Rail (Huddersfield to Westtown (Dewsbury) Improvements) Order 2022 (S.I. 2022/1067), arts. 1, 38(3) (with art. 46(2), Sch. 19 para. 61)
- C158Act modified (28.3.2013) by The Network Rail (Seaham Level Crossing) Order 2013 (S.I. 2013/533), art. 10
- F55Words in s. 22(1) substituted (6.4.2012) by Localism Act 2011 (c. 20), ss. 232(6)(a), 240(2) (with s. 232(8)); S.I. 2012/628, art. 8(d) (with arts. 9, 12, 13, 16, 18-20) (as amended (3.8.2012) by S.I. 2012/2029, arts. 2, 4)
- F56Words in s. 6E(2)(c) omitted (31.1.2024) by virtue of Levelling-up and Regeneration Act 2023 (c. 55), ss. 188(2)(b), 255(7) (with s. 247); S.I. 2024/92, reg. 2(o)
- C159Pt. 1 applied (28.4.2025) by The Rampion 2 Offshore Wind Farm Order 2025 (S.I. 2025/468), arts. 1, 11(6), 18(10), 19(6), 25(4), 30(4), 31(8), 32(8), 42(3), 43(5), 54(3) (with arts. 18(9), 25(5), 30(5), 31(10)(14), 32(9), 47, 48, Sch. 10)
- C160Act modified (15.10.2020) by The Great Yarmouth Third River Crossing Development Consent Order 2020 (S.I. 2020/1075), Sch. 7 para. 2
- C161Act applied (with modifications) (8.1.2026) by The Five Estuaries Offshore Wind Farm Order 2025 (S.I. 2025/1376), art. 1, Sch. 8 paras. 1, 2 (with arts. 39, 40, Sch. 9)
- C162Act modified (25.5.2020) by The West Midlands Rail Freight Interchange Order 2020 (S.I. 2020/511), Sch. 12 para. 2
- F57S. 15 omitted (22.9.2017) by virtue of Neighbourhood Planning Act 2017 (c. 20), ss. 32(4)(a), 46(1); S.I. 2017/936, reg. 3(b) (with reg. 4)
- C163Act applied (with modifications) (9.5.2024) by The Sheringham Shoal and Dudgeon Extensions Offshore Wind Farm Order 2024 (S.I. 2024/564), art. 1, Sch. 8 paras. 1, 2 (with arts. 35, 36, Sch. 14)
- C164Act modified (12.1.2016) by The London Underground (Bank Station Capacity Upgrade) Order 2015 (S.I. 2015/2044), art. 28(3)
- F58Sch. 2A para. 1A and cross-heading inserted (18.2.2026) by Planning and Infrastructure Act 2025 (c. 34), ss. 114(3), 118(5)(h) (with s. 116)
- C165S. 4 applied (with modifications) (1.10.2011) by The Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011 (S.I. 2011/2055), regs. 1, 61(5)
- C166Act modified (31.12.2020) by The Network Rail (Cambridgeshire Level Crossing Reduction) Order 2020 (S.I. 2020/1485), art. 1, Sch. 14 para. 2
- C167Pt. 1 applied (3.11.2022) by The Network Rail (Huddersfield to Westtown (Dewsbury) Improvements) Order 2022 (S.I. 2022/1067), arts. 1, 14(6)(7), 16(6), 21(3), 23(10), 24(15), 25(4), 33(3), 34(7), 35(7), 36(5), 39(5), 43(3) (with arts. 24(16), 33(5), 34(8), 35(8), 39(6), 46(2), Sch. 18 para. 2, Sch. 19 para. 61)
- C168Act modified (14.4.2020) by The Reinforcement to the North Shropshire Electricity Distribution Network Order 2020 (S.I. 2020/325), art. 1, Sch. 4 para. 3 (with art. 7)
- C169Act applied (with modifications) (15.2.2025) by The West Burton Solar Project Order 2025 (S.I. 2025/116), art. 1, Sch. 10 paras. 1, 3 (with art. 47, Sch. 15)
- C170Pt. 1 applied (9.2.2021) by The A1 Birtley to Coal House Development Consent Order 2021 (S.I. 2021/74), arts. 1, 15(6), 16(4), 21(10), 22(5), 27(5), 31(4)(5), 32(6), 33(8), 37(3), 38(4) (with arts. 5, 21(9), 32(8), 33(9), 35, Sch. 27 para. 36)
- F59Ss. 6A-6E substituted for ss. 6-9 (22.9.2017) by Neighbourhood Planning Act 2017 (c. 20), ss. 32(3), 46(1); S.I. 2017/936, reg. 3(b) (with reg. 4 and regs. 6, 7 which amend the new s. 6E(2)(b)(c))
- C171Act modified (16.4.2021) by The Network Rail (Chart Leacon) Order 2021 (S.I. 2021/419), arts. 1, 10(3), Sch. 1 para. 2
- C172S. 4 applied (13.11.2025) by The Stonestreet Green Solar Order 2025 (S.I. 2025/1175), art. 1, Sch. 12 para. 1(10) (with art. 40, Sch. 13)
- C173Act applied (with modifications) (14.6.2024) by The A1 in Northumberland: Morpeth to Ellingham Development Consent Order 2024 (S.I. 2024/733), art. 1, Sch. 7 paras. 1, 2 (with art. 6, Sch. 10)
- C174Pt. 1 applied (27.4.2022) by The Little Crow Solar Park Order 2022 (S.I. 2022/436), arts. 1, 10(5), 16(3)
- C175Act modified (8.9.2022) by The A428 Black Cat to Caxton Gibbet Development Consent Order 2022 (S.I. 2022/934), arts. 1, 32 (with arts. 23, 53, Sch. 9 para. 65)
- C176Pt. 1 applied (23.4.2025) by The Cambridge Waste Water Treatment Plant Relocation Order 2025 (S.I. 2025/452), arts. 1, 12(7), 20(9), 21(6), 23(3), 24(4), 25(4), 31(6), 35(7), 36(7), 43(4) (with art. 50)
- F60S. 21 repealed (6.4.2012) by Localism Act 2011 (c. 20), ss. 232(5), 240(2), Sch. 25 Pt. 34 (with s. 232(8)); S.I. 2012/628, art. 8(d)(e) (with arts. 9, 12, 13, 16, 18-20) (as amended (3.8.2012) by S.I. 2012/2029, arts. 2, 4)
- C177Act modified (2.8.2022) by The Network Rail (Oxford Station Phase 2 Improvements (Land Only)) (No. 2) Order 2022 (S.I. 2022/872), arts. 1(1), 11(3), Sch. 1 paras. 1, 2 (with art. 11(1)(2))
- C178S. 5 applied (with modifications) (1.4.2010) by The Conservation of Habitats and Species Regulations 2010 (S.I. 2010/490), regs. 1(2), 28(6) (with reg. 125)
- C179Act modified (5.4.2024) by The National Grid (Yorkshire Green Energy Enablement Project) Development Consent Order 2024 (S.I. 2024/393), arts. 1, 30(3) (with art. 44, Sch. 15)
- C180Act applied (with modifications) (31.5.2025) by The East Yorkshire Solar Farm Order 2025 (S.I. 2025/585), art. 1, Sch. 10 paras. 1, 3 (with art. 49, Sch. 14)
- C181Act applied (with modifications) (19.12.2017) by The Network Rail (Buxton Sidings Extension) Order 2017 (S.I. 2017/1150), Sch. 7 paras. 1, 2 (with art. 32(2))
- C182Act modified (28.10.2009) by Network Rail (Reading) (Land Acquisition) Order 2009 (S.I. 2009/2728), art. 14(3)
- C183Act applied (with modifications) (12.10.2025) by The Gatwick Airport (Northern Runway Project) Development Consent Order 2025 (S.I. 2025/1054), art. 1, Sch. 8 paras. 1, 3 (with arts. 5, 9(6), 43, Sch. 9)
- C184S. 4 applied (with modifications) (1.10.2024) by The Land Compensation (Additional Compensation) (England) Regulations 2024 (S.I. 2024/915), regs. 1(1), 13(2)
- F61S. 5A(5A) inserted (3.2.2017) by Housing and Planning Act 2016 (c. 22), s. 216(3), Sch. 17 para. 4(2); S.I. 2017/75, reg. 3(g)
- C185Act modified (19.2.2021) by The A303 Sparkford to Ilchester Dualling Development Consent Order 2021 (S.I. 2021/125), art. 1, Sch. 6 para. 2 (with arts. 4, 47)
- C186Act modified (21.4.2015) by The Network Rail (Ordsall Chord) Order 2015 (S.I. 2015/780), art. 30(3) (with art. 36(2))
- C187Pt. 1 applied (29.12.2025) by The Helios Renewable Energy Project Order 2025 (S.I. 2025/1372), arts. 1, 13, 18, 19, 23, 28, 29, 30, 37, 38 (with Sch. 9)
- C188Act applied (with modifications) (17.2.2025) by The Heckington Fen Solar Park Order 2025 (S.I. 2025/85), art. 1, Sch. 9 paras. 1, 3 (with art. 43, Sch. 13)
- C189Pt. 1 applied (8.9.2022) by The A428 Black Cat to Caxton Gibbet Development Consent Order 2022 (S.I. 2022/934), arts. 1, 16(5), 17(6), 21(11), 22(6), 29(5), 36(4), 37(6), 38(9), 42(3), 43(5), 56(3) (with arts. 21(9), 23, 36(5), 37(8), 38(10), 40, 53, Sch. 9 para. 65)
- F62S. 34(1) substituted (E.) (1.10.2006) by Church of England (Miscellaneous Provisions) Measure 2006 (No. 1), s. 16(2), Sch. 5 para. 8(a); 2006 No. 2, Instrument made by Archbishops
- C190Act applied (24.4.2025) by The London Luton Airport Expansion Development Consent Order 2025 (S.I. 2025/463), arts. 1, 41 (with art. 39, Sch. 8)
- C191Act applied (with modifications) (27.9.2024) by The Cottam Solar Project Order 2024 (S.I. 2024/943), art. 1, Sch. 10 paras. 1, 3 (with art. 48, Sch. 15)
- C192Act applied (with modifications) (15.4.2025) by The A122 (Lower Thames Crossing) Development Consent Order 2025 (S.I. 2025/462), art. 1, Sch. 9 paras. 1, 2 (with arts. 5, 43, 53(7), Sch. 14) (as amended (12.9.2025) by by S.I. 2025/1014, art. 1, Sch.
- C193Act modified (25.3.2022) by The Bridgwater Tidal Barrier Order 2022 (S.I. 2022/299), arts. 1, 40(3), Sch. 4 para. 2 (with art. 55)
- C194Pt. 1 applied (11.2.2021) by High Speed Rail (West Midlands - Crewe) Act 2021 (c. 2), ss. 8(8), 14(6), 64(1), Sch. 2 para. 11(6), Sch. 4 para. 4(3), Sch. 14 para. 4(2), Sch. 15 para. 4(5), Sch. 15 para. 7(4), Sch. 15 para. 8(5) (with Sch. 14 para. 4(3), Sch. 15 para. 4(6), Sch. 15 para. 7(5), Sch. 15 para. 8(6))
- F63Words in s. 5A(9)(b) omitted (13.7.2016) by virtue of Housing and Planning Act 2016 (c. 22), s. 216(3), Sch. 16 para. 1(b); S.I. 2016/733, reg. 3(j)
- C195Act modified (29.12.2008) by Network Rail (Thameslink) (Land Acquisition) Order 2008 (S.I. 2008/3163), art. 10(3) (with art. 10(1)(2))
- C196Act modified (3.4.2019) by The Millbrook Gas Fired Generating Station Order 2019 (S.I. 2019/578), art. 1, Sch. 8 para. 3
- C197Pt. 1 applied (27.11.2025) by The Cory Decarbonisation Project Order 2025 (S.I. 2025/1227), arts. 1, 15, 16, 22, 23, 24, 32, 36, 37, 38 (with Sch. 12)
- C198Act applied (23.4.2025) by The Cambridge Waste Water Treatment Plant Relocation Order 2025 (S.I. 2025/452), arts. 1, 38 (with art. 50)
- C199S. 5 applied by 2003 c. 21, Sch. 3A para. 84(3)(a) (as inserted (28.12.2017) by Digital Economy Act 2017 (c. 30), s. 118(6), Sch. 1 (with Sch. 2); S.I. 2017/1286, reg. 2(b))
- F64S. 14A inserted (31.3.2024 for W. for specified purposes, 30.4.2024 for E.) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 190(2)(a), 255(7) (with s. 247); S.I. 2024/92, reg. 4 (with reg. 6(6)); S.I. 2024/389, reg. 2(l)
- F65Ss. 14, 15 substituted (6.4.2012) for ss. 14-16 by Localism Act 2011 (c. 20), ss. 232(2), 240(2) (with s. 232(8)); S.I. 2012/628, art. 8(d) (with arts. 9, 12, 13, 16, 18-20) (as amended (3.8.2012) by S.I. 2012/2029, arts. 2, 4)
- C200Pt. 1 applied (2.12.2021) by The South Humber Bank Energy Centre Order 2021 (S.I. 2021/1259), arts. 1, 13(5), 16(5), 17(3) (with Sch. 8 para. 48)
- C201Act applied (with modifications) (3.3.2026) by The Network Rail (Kettering to Wigston South Junction and Napsbury Lane) (Land Acquisition) Order 2026 (S.I. 2026/141), art. 1, Sch. 2 paras. 1, 2
- C202Act modified (3.10.2018) by The A19/A184 Testos Junction Alteration Development Consent Order 2018 (S.I. 2018/994), Sch. 6 para. 2 (with arts. 3(3), 5)
- F66Sch. 2A inserted (31.3.2024 for W. for specified purposes, 30.4.2024 for E.) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 190(2)(c), 255(7) (with s. 247); S.I. 2024/92, reg. 4 (with reg. 6(6)); S.I. 2024/389, reg. 2(l)
- C203Act modified (14.10.2008) by Felixstowe Branch Line and Ipswich Yard Improvement Order 2008 (S.I. 2008/2512), art. 30 (with art. 36(3))
- C204Act applied (23.9.2016) by The M4 Motorway (Junctions 3 to 12) (Smart Motorway) Development Consent Order 2016 (S.I. 2016/863), art. 16(3)
- F67S. 20(d) repealed (6.4.2012) by Localism Act 2011 (c. 20), ss. 232(4)(c), 240(2), Sch. 25 Pt. 34 (with s. 232(8)); S.I. 2012/628, art. 8(d)(e) (with arts. 9, 12, 13, 16, 18-20) (as amended (3.8.2012) by S.I. 2012/2029, arts. 2, 4)
- C205Pt. 1 applied (13.3.2024) by The Medworth Energy from Waste Combined Heat and Power Facility Order 2024 (S.I. 2024/230), arts. 1, 13(6), 14(3), 19(6), 20(10), 21(3), 27(4), 31(4), 32(6), 33(7) (with arts. 20(9), 27(5), 31(5), 32(7)(12), 33(8), Sch. 11 paras. 4, 5, 22, 37, 47, 80, 82, 110)
- C206S. 4 applied (with modifications) (26.11.2008 for specified purposes, 1.3.2010 in so far as not already in force) by Planning Act 2008 (c. 29), ss. 165(6), 241(1), 241(8) (with s. 226); S.I. 2010/101, art. 3(j) (with art. 6)
- C207Act applied (with modifications) (3.8.2024) by The Gate Burton Energy Park Order 2024 (S.I. 2024/807), art. 1, Sch. 10 paras. 1, 3 (with art. 45, Sch. 14)
- C208Pt. 1 applied (7.12.2022) by The A417 Missing Link Development Consent Order 2022 (S.I. 2022/1248), arts. 1, 15(5), 16(6), 22(10), 23(5), 29(5), 33(4), 34(6), 35(8), 40(4) (with arts. 4, 29(6), 33(5), 34(7), 35(9), 37)
- C209Act applied (with modifications) (14.8.2025) by The Byers Gill Solar Order 2025 (S.I. 2025/934), art. 1, Sch. 9 paras. 1, 3 (with art. 43, Sch. 11)
- C210Pt. 1 applied (1.1.2022) by The Norfolk Boreas Offshore Wind Farm Order 2021 (S.I. 2021/1414), arts. 1, 11(9), 16(7), 21(4), 25(4), 26(6), 27(8), 35(3), 36(5) (with arts. 21(5), 26(7), 27(9), 41, 42, Sch. 17 para. 66)
- C211Act applied (with modifications) (10.3.2023) by The A47 Wansford to Sutton Development Consent Order 2023 (S.I. 2023/218), art. 1, Sch. 6 paras. 1, 2 (with arts. 4, 50)
- C212Act modified (19.12.2017) by The Network Rail (Buxton Sidings Extension) Order 2017 (S.I. 2017/1150), art. 26(3) (with art. 32(2))
- C213Pt. 1 applied (13.7.2022) by The A47 Blofield to North Burlingham Development Consent Order 2022 (S.I. 2022/738), arts. 1, 16(5), 17(7), 22(10), 23(5), 29(5), 33(4), 34(6), 35(7), 39(3) (with arts. 4, 29(6), 33(5), 50)
- C214S. 4 applied (with modifications) (1.4.2010) by The Conservation of Habitats and Species Regulations 2010 (S.I. 2010/490), regs. 1(2), 28(8)(b) (with reg. 125)
- F68Words in s. 5 substituted (1.6.2009) by The Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307), art. 1, Sch. 1 para. 40 (with Sch. 5)
- F69S. 2 omitted (1.6.2009) by virtue of The Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307), art. 1, Sch. 1 para. 38 (with Sch. 5)
- F70S. 6D(7) inserted (31.1.2024) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 188(1)(c), 255(7) (with s. 247); S.I. 2024/92, reg. 2(o)
- C215Act applied (19.8.2014) by The Network Rail (Huyton) Order 2014 (S.I. 2014/2027), art. 24(3) (with art. 31(2))Act modified (24.9.2014) by The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 (S.I. 2014/2384), arts. 1, 38(3)
- C216Act applied (with modifications) (22.4.2022) by The East Anglia TWO Offshore Wind Farm Order 2022 (S.I. 2022/433), art. 1(2), Sch. 8 para. 3 (with arts. 40, 41)
- C217Act modified (25.2.2020) by The Network Rail (East West Rail) (Bicester to Bedford Improvements) Order 2020 (S.I. 2020/114), Sch. 13 para. 2 (with art. 37(2))
- C218Pt. 1 applied (3.8.2023) by The Hornsea Four Offshore Wind Farm Order 2023 (S.I. 2023/800), arts. 1, 10(6), 16(10), 17(5), 22(5), 27(4), 28(6)(14), 29(7)(14), 36(4), 37(4) (with arts. 16(9), 22(6), 27(5), 28(7)(11), 29(8), 42, 43, Sch. 9 Pt. 1 para. 4, Sch. 9 Pt. 3 para. 6(1), Sch. 9 Pt. 4 para. 2, Sch. 9 Pt. 9 para. 4)
- C219Pt. 1 applied (3.3.2026) by The Network Rail (Kettering to Wigston South Junction and Napsbury Lane) (Land Acquisition) Order 2026 (S.I. 2026/141), arts. 1, 8(5), 9(7), 11(4), 12(3)
- C220Act applied (with modifications) by 1990 c. 8, s. 165ZA(3) (as inserted (15.1.2012) by Localism Act 2011 (c. 20), s. 240(1)(l), Sch. 22 para. 33)
- C221Pt. 1 applied (25.4.2024) by The Network Rail (Church Fenton Level Crossing Reduction) Order 2024 (S.I. 2024/526), arts. 1, 8(3), 11(6), 17(15), 22(4), 23(6), 24(7), 26(5), 30(3) (with arts. 22(5), 23(7), 24(8), 26(6), 39, 40)
- C222Act applied (with modifications) (11.3.2024) by The Net Zero Teesside Order 2024 (S.I. 2024/174), art. 1, Sch. 8 paras. 1, 3 (with arts. 42, 43, Sch. 12)
- C223Act modified (6.11.2013) by The Transport for Greater Manchester (Light Rapid Transit System) (Second City Crossing) Order 2013 (S.I. 2013/2587), art. 35(3) (with arts. 42, 43)
- C224Act applied (with modifications) (11.3.2026) by The Fenwick Solar Farm Order 2026 (S.I. 2026/151), art. 1, Sch. 10 paras. 1, 3 (with Sch. 14)
- C225Act applied (1.12.2008) by Housing and Regeneration Act 2008 (c. 17), s. 325(1), Sch. 2 para. 7(2); S.I. 2008/3068, art. 2(1)(d) (with arts. 6-13)
- F71S. 17(5A)-(5C) substituted for s. 17(5)-(8) (31.1.2025) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 189(3)(d), 255(7) (with s. 247); S.I. 2024/92, reg. 5 (with reg. 6(3)-(5))
- C226Act applied (2.8.2016) by The Midland Metro (Wolverhampton City Centre Extension) Order 2016 (S.I. 2016/684), art. 36(3) (with arts. 46, 47, Sch. 9 para. 4, Sch. 10 para. 12(2))
- C227Pt. 1 applied (10.3.2022) by The Thurrock Flexible Generation Plant Development Consent Order 2022 (S.I. 2022/157), arts. 1, 13(6), 17(5), 23(5), 27(4), 28(6), 29(7), 35(3) (with art. 27(5), Sch. 8 Pt. 6 para. 19)
- C228Act modified (25.10.2019) by The Drax Power (Generating Stations) Order 2019 (S.I. 2019/1315), art. 1, Sch. 9 para. 3
- F72Words in s. 6E(3) substituted (31.1.2024) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 188(2)(c), 255(7) (with s. 247); S.I. 2024/92, reg. 2(o)
- C229Act modified (29.7.2014) by The Felixstowe Branch Line (Land Acquisition) Order 2014 (S.I. 2014/1821), art. 11(3)
- F73Words in s. 14(5) substituted (31.1.2025) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 189(2)(c), 255(7) (with s. 247); S.I. 2024/92, reg. 5 (with reg. 6(3)-(5))
- C230Pt. 1 applied (22.10.2025) by The A46 Newark Bypass Development Consent Order 2025 (S.I. 2025/1090), arts. 1, 18(5), 19(6), 24(11), 25(5), 30(5), 38(4), 39(6), 40(9), 45(3), 46(10), 52(3), 57(5) (with arts. 4, 9, 24(9), 30(6), 39(8), 40(10), 51, Sch. 9)
- C231Act applied (with modifications) (8.9.2022) by The A428 Black Cat to Caxton Gibbet Development Consent Order 2022 (S.I. 2022/934), art. 1, Sch. 6 paras. 1, 2 (with arts. 23, 53, Sch. 9 para. 65)
- C232Act modified (5.12.2022) by The Portishead Branch Line (MetroWest Phase 1) Order 2022 (S.I. 2022/1194), arts. 1, 36 (with art. 51)
- C233S. 4 applied (with modifications) (1.1.2018) by The Water Abstraction (Transitional Provisions) Regulations 2017 (S.I. 2017/1047), regs. 1, 11(2) (with reg. 8)
- C234S. 4 applied (with modifications) (4.11.2024) by Historic Environment (Wales) Act 2023 (asc 3), ss. 203(2), 212(2) (with Sch. 14 paras. 1-3); S.I. 2024/860, art. 3(c)
- F74S. 5(2A) inserted (22.9.2017) by Neighbourhood Planning Act 2017 (c. 20), ss. 32(2), 46(1); S.I. 2017/936, reg. 3(b) (with reg. 4)
- F75Words in s. 19(3) substituted (31.1.2025) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 189(5)(a), 255(7) (with s. 247); S.I. 2024/92, reg. 5 (with reg. 6(3)-(5))
- C235Act applied (with modifications) (28.4.2025) by The Rampion 2 Offshore Wind Farm Order 2025 (S.I. 2025/468), art. 1, Sch. 8 paras. 1, 3 (with arts. 47, 48, Sch. 10)
- C236Pt. 1 applied (13.11.2025) by The Stonestreet Green Solar Order 2025 (S.I. 2025/1175), arts. 1, 13, 17, 20, 26, 30, 32, 38, 43 (with art. 40, Sch. 13)
- C237Act applied (with modifications) (25.4.2024) by The Network Rail (Church Fenton Level Crossing Reduction) Order 2024 (S.I. 2024/526), art. 1, Sch. 10 paras. 1, 2
- C238S. 5 applied (30.11.2017) by The Conservation of Habitats and Species Regulations 2017 (S.I. 2017/1012), regs. 1(2), 30(6)
- C239Act applied (with modifications) (27.2.2025) by The Associated British Ports (Immingham Green Energy Terminal) Order 2025 (S.I. 2025/165), arts. 1, 38(3), Sch. 11 paras. 1, 3 (with arts. 48, 59, Sch. 14)
- F76Words in s. 17(10) substituted (31.1.2025) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 189(3)(e)(i), 255(7) (with s. 247); S.I. 2024/92, reg. 5 (with reg. 6(3)-(5))
- C240Act modified (27.7.2023) by The Boston Alternative Energy Facility Order 2023 (S.I. 2023/778), arts. 1, 39(2) (with arts. 5, 53, Sch. 8 paras. 6, 64)
- C241Act applied (16.12.2015) by The Network Rail (Tinsley Chord) Order 2015 (S.I. 2015/1876), art. 21(3)
- F77Words in s. 31(4) inserted (6.4.2018) by Housing and Planning Act 2016 (c. 22), ss. 193(3), 216(3); S.I. 2018/251, reg. 4(d) (with reg. 6)
- C242Pt. 1 applied (22.1.2021) by The Hornsea Three Offshore Wind Farm Order 2020 (S.I. 2020/1656), arts. 1, 10(6), 16(10), 17(5), 21(4), 25(4)(5), 26(6), 27(7), 34(3), 35(5) (with arts. 16(9), 21(5), 26(7), 27(8), 40, 41, Sch. 9 Pt. 5 para. 18)
- C243S. 5A applied (with modifications) (2.12.2020) by The Network Rail (London to Corby) (Land Acquisition) Order 2020 (S.I. 2020/1259), arts. 1(1), 7(4), Sch. 4 para. 2
- C244Pt. 1 applied (14.8.2025) by The Byers Gill Solar Order 2025 (S.I. 2025/934), arts. 1, 13(6), 19(10), 20(5), 24(4), 29(4), 30(7), 31(7), 38(3), 39(4) (with arts. 19(9), 24(5), 29(5), 30(8)(10)(12), 31(8), 43, Sch. 11)
- F78S. 32(3) inserted (31.3.2024 for W. for specified purposes, 30.4.2024 for E.) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 190(2)(b), 255(7) (with s. 247); S.I. 2024/92, reg. 4 (with reg. 6(6)); S.I. 2024/389, reg. 2(l)
- C245Pt. 1 applied (8.1.2026) by The Five Estuaries Offshore Wind Farm Order 2025 (S.I. 2025/1376), arts. 1, 13, 14, 19, 20, 25, 29, 30, 32, 36, 37 (with arts. 39, 40, Sch. 9)
- C246Pt. 1 applied (19.2.2021) by The A303 Sparkford to Ilchester Dualling Development Consent Order 2021 (S.I. 2021/125), arts. 1, 15(5), 16(10), 21(10), 22(5), 28(5), 32(4), 33(6), 34(7), 38(3) (with arts. 4, 21, 28(6), 32(5), 33(7), 34(8), 36, 47)
- C247Act applied (with modifications) (12.10.2018) by The Eggborough Gas Fired Generating Station Order 2018 (S.I. 2018/1020), Sch. 9 para. 3 (with arts. 6, 42)
- F79S. 5A inserted (31.10.2004) by Planning and Compulsory Purchase Act 2004 (c. 5), s. 103(2); S.I. 2004/2593, art. 2(a)
- C248Act modified (11.6.2020) by The M42 Junction 6 Development Consent Order 2020 (S.I. 2020/528), art. 1, Sch. 9 para. 2 (with art. 37)
- C249Act applied (with modifications) (28.3.2024) by The A66 Northern Trans-Pennine Development Consent Order 2024 (S.I. 2024/360), art. 1, Sch. 5 paras. 1, 2 (with arts. 18, 35, Sch. 9)
- C250Pt. 1 applied (24.4.2025) by The London Luton Airport Expansion Development Consent Order 2025 (S.I. 2025/463), arts. 1, 13(5), 14(3), 20(10), 21(6), 22(4), 28(5), 32(4), 33(6), 34(9) (with art. 39, Sch. 8)
- C251Act applied (13.7.2022) by The A47 Blofield to North Burlingham Development Consent Order 2022 (S.I. 2022/738), arts. 1, 45, Sch. 6 paras. 1, 2 (with arts. 4, 50)
- C252Act applied (with modifications) (7.12.2022) by The A57 Link Roads Development Consent Order 2022 (S.I. 2022/1206), art. 1, Sch. 6 paras. 1, 2 (with art. 5)
- C253S. 4 applied (with modifications) (E.) (1.3.2009) by Environmental Damage (Prevention and Remediation) Regulations 2009 (S.I. 2009/153), reg. 1(1), Sch. 6 para. 7(2)
- F80Words in s. 5A(5B)(b) inserted (31.1.2024) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 186(7)(c), 255(7) (with s. 247); S.I. 2024/92, reg. 2(m) (with reg. 6(2))
- C254Act applied (with modifications) (11.8.2022) by The Sizewell C (Nuclear Generating Station) Order 2022 (S.I. 2022/853), art. 1, Sch. 16 para. 3 (with arts. 62, 76, 87, Sch. 19 paras. 4, 78)
- C255S. 5 applied by 1985 c. 68, s. 584B(5) (as substituted (6.4.2006 for E., 16.6.2006 for W.) by Housing Act 2004 (c. 34), s. 270(4)(5)(f), Sch. 15 para. 31; S.I. 2006/1060, art. 2(1)(d) (with Sch.); S.I. 2006/1535, art. 2(b) (with Sch.))
- F81S. 20(b) repealed (6.4.2012) by Localism Act 2011 (c. 20), ss. 232(4)(b), 240(2), Sch. 25 Pt. 34 (with s. 232(8)); S.I. 2012/628, art. 8(d)(e) (with arts. 9, 12, 13, 16, 18-20) (as amended (3.8.2012) by S.I. 2012/2029, arts. 2, 4)
- C256Pt. 1 applied (18.7.2023) by The Longfield Solar Farm Order 2023 (S.I. 2023/734), arts. 1, 11(5), 16(10), 17(5), 21(4), 26(4), 27(7), 28(7), 36(3), 37(4) (with arts. 16(9), 21(5), 26(5), 27(8)(11)(13), 28(8))
- C257Pt. 1 applied (5.11.2025) by The Tillbridge Solar Order 2025 (S.I. 2025/1105), arts. 1, 12(5), 13(7), 14(3), 19(10), 20(5), 24(4), 29(4), 30(7), 31(7), 39(3), 40(5) (with arts. 12(8), 19(9), 24(5), 29(5), 30(8)(11)(13), 31(8), 49, Sch. 15)
- C258S. 13 applied (2.4.2004) by Docklands Light Railway (Woolwich Arsenal Extension) Order 2004 (S.I. 2004/757), arts. 1, 31(10)
- F82Words in Sch. 2A para. 7(1)(b) inserted (18.2.2026) by Planning and Infrastructure Act 2025 (c. 34), ss. 114(4), 118(5)(h) (with s. 116)
- C259Pt. 1 applied (22.4.2022) by The East Anglia ONE North Offshore Wind Farm Order 2022 (S.I. 2022/432), arts. 1(2), 10(3), 11(4), 12(6), 17(6), 21(4), 25(4), 26(6), 27(7), 34(3), 35(4) (with arts. 21(5), 26(7), 27(8), 40, 41)
- C260Act modified (9.2.2021) by The A1 Birtley to Coal House Development Consent Order 2021 (S.I. 2021/74), art. 1, Sch. 7 para. 2 (with art. 5, Sch. 27 para. 36)
- F83S. 38(3)-(9) inserted (18.2.2026) by Planning and Infrastructure Act 2025 (c. 34), ss. 105(2), 118(5)(a) (with s. 116)
- C261Pt. 1 applied (11.3.2024) by The Net Zero Teesside Order 2024 (S.I. 2024/174), arts. 1, 13(5), 18(3), 19(10), 20(5), 26(5), 30(4), 31(7), 32(8) (with arts. 19(9), 32(9), 42, 43, Sch. 12)
- C262Pt. 1 applied (2.12.2020) by The Network Rail (London to Corby) (Land Acquisition) Order 2020 (S.I. 2020/1259), arts. 1(1), 9(4), 10(6), 11(4), 12(7), 13(5), 15(4), 19(14) (with art. 9(5))
- C263Pt. 1 applied (15.3.2021) by The Wheelabrator Kemsley K3 Generating Station Order 2021 (S.I. 2021/173), arts. 1, 11(7), 12(3)
- C264Pt. 1 applied (27.9.2024) by The Cottam Solar Project Order 2024 (S.I. 2024/943), arts. 1, 11(5), 12(3), 18(10), 19(5), 23(4), 28(4), 29(7), 30(7), 38(3), 39(4) (with arts. 18(9), 23(5), 28(5), 29(8)(11)(13), 30(8), 48, Sch. 15)
- C265Act applied (with modifications) (15.12.2014) by The London Underground (Northern Line Extension) Order 2014 (S.I. 2014/3102), art. 33(3) (with Sch. 8 para. 45)
- C266Pt. 1 applied (29.12.2022) by The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022 (S.I. 2022/1396), arts. 1, 15(5), 16(3), 17(3), 22(5), 23(11), 26(4), 27(7), 28(7), 33(3), 34(10) (with arts. 22(6), 26(5), 27(8)(13), 28(8), 32, 34(9), Sch. 10 paras. 26(2), 68)
- C267Act modified (19.1.2021) by The Network Rail (Suffolk Level Crossing Reduction) Order 2020 (S.I. 2020/1663), art. 1, Sch. 8 para. 2
- C268Pt. 1 applied (25.3.2022) by The Bridgwater Tidal Barrier Order 2022 (S.I. 2022/299), arts. 1, 11(6), 12(4), 15(3), 21(10), 23(6), 24(3), 36(4), 38(7), 41(7) (with arts. 36(5), 55)
- C269Act modified (21.4.2011) by The Network Rail (Hitchin (Cambridge Junction)) Order 2011 (S.I. 2011/1072), art. 27
- F84Words in s. 22(2) substituted (6.4.2012) by Localism Act 2011 (c. 20), ss. 232(6)(b), 240(2) (with s. 232(8)); S.I. 2012/628, art. 8(d) (with arts. 9, 12, 13, 16, 18-20) (as amended (3.8.2012) by S.I. 2012/2029, arts. 2, 4)
- C270Act modified (8.8.2017) by The Wrexham Gas Fired Generating Station Order 2017 (S.I. 2017/766), Sch. 7 para. 3
- F85Sch. 1 omitted (22.9.2017) by virtue of Neighbourhood Planning Act 2017 (c. 20), ss. 32(4)(b), 46(1); S.I. 2017/936, reg. 3(b) (with reg. 4)
- C271Act modified (18.6.2020) by The A63 (Castle Street Improvement, Hull) Development Consent Order 2020 (S.I. 2020/556), art. 1, Sch. 6 para. 2 (with arts. 5, 44)
- C272Pt. 1 applied (5.3.2022) by The Norfolk Vanguard Offshore Wind Farm Order 2022 (S.I. 2022/138), arts. 1, 11(6), 16(6), 21(4), 25(4), 26(6), 27(8), 35(3), 36(5) (with arts. 21(5), 25(5), 26(7), 27(9), 41, 42, Sch. 16)
- F86Words in s. 31(4) substituted (1.6.2009) by The Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307), art. 1, Sch. 1 para. 43 (with Sch. 5)
- F87S. 14(2A)(2B) substituted for s. 14(3)(4) (31.1.2025) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 189(2)(b), 255(7) (with s. 247); S.I. 2024/92, reg. 5 (with reg. 6(3)-(5))
- C273Act applied (with modifications) (5.9.2017) by The London Overground (Barking Riverside Extension) Order 2017 (S.I. 2017/830), art. 31 (with Sch. 8 para. 20)
- C274Pt. 1 applied (3.8.2024) by The Gate Burton Energy Park Order 2024 (S.I. 2024/807), arts. 1, 11(5), 16(10), 17(5), 21(4), 26(4), 27(7), 28(7), 36(3), 37(4) (with arts. 21(5), 27(8)(11)(13), 28(8), 45, Sch. 14)
- C275Act applied (with modifications) (30.9.2025) by The M60/M62/M66 Simister Island Interchange Development Consent Order 2025 (S.I. 2025/1018), art. 1, Sch. 6 paras. 1, 2 (with arts. 5, 34, Sch. 9)
- C276Pt. 1 applied (7.12.2022) by The A57 Link Roads Development Consent Order 2022 (S.I. 2022/1206), arts. 1, 14(5), 15(5), 20(10), 21(5), 26(5), 30(4), 31(6), 32(7), 36(6), 38(4) (with art. 5)
- C277Pt. 1 applied (2.8.2022) by The Network Rail (Oxford Station Phase 2 Improvements (Land Only)) Order 2022 (S.I. 2022/871), arts. 1, 8(7), 9(7), 12(5), 14(3), 15(3), 16(14) (with art. 12(6))
- C278S. 4 applied (with modifications) (15.12.2025) by Infrastructure (Wales) Act 2024 (asc 3), ss. 108(7), 147(2) (with s. 84(5)); S.I. 2025/698, art. 3(h)
- C279Pt. 1 applied (2.8.2023) by The Rother Valley Railway (Bodiam to Robertsbridge Junction) Order 2023 (S.I. 2023/815), arts. 1, 11(4), 12(5), 17(13), 22(6), 23(7), 25(4), 28(3) (with art. 42)
- F88S. 4(A1) inserted (1.6.2009) by The Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307), art. 1, Sch. 1 para. 39(a) (with Sch. 5)
- C280Act modified (1.8.2022) by The Northumberland Line Order 2022 (S.I. 2022/820), arts. 1, 22(3), Sch. 6 para. 2 (with Sch. 10 paras. 21, 43)
- C281Pt. 1 applied (4.4.2025) by The North Lincolnshire Green Energy Park Order 2025 (S.I. 2025/362), arts. 1, 14(4), 15(4), 27(4), 31(4), 32(6), 33(8), 38(5), 39(3), 40(5) (with arts. 27(5), 31(5), 32(7), 33(9), Sch. 14)
- F89Words in s. 5A(7) substituted (1.6.2009) by The Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307), art. 1, Sch. 1 para. 41 (with Sch. 5)
- C282Act applied (with modifications) (15.8.2013) by The North Blyth Biomass Power Station Order 2013 (S.I. 2013/1873), arts. 15, 18 (with art. 30)
- F90Words in s. 5A(6) substituted (3.2.2017) by Housing and Planning Act 2016 (c. 22), s. 216(3), Sch. 17 para. 4(3); S.I. 2017/75, reg. 3(g)
- C283Pt. 1 applied (1.5.2025) by The Viking CCS Carbon Dioxide Pipeline Order 2025 (S.I. 2025/509), arts. 1(2), 12(4), 13(5), 16(3), 20(6), 21(10), 27(4), 31(4), 32(6), 33(7), 39(3), 40(4) (with arts. 27(5), 31(5), 32(7), 33(8), 41, Sch. 9)
- C284S. 13 applied (25.11.2005) by Docklands Light Railway (Capacity Enhancement) Order 2005 (S.I. 2005/3105), arts. 1, 31(10) (with arts. 3(5), 15(3))
- C285S. 5A applied (with modifications) (1.1.2018) by The Water Abstraction (Transitional Provisions) Regulations 2017 (S.I. 2017/1047), regs. 1, 12(1) (with reg. 8)
- C286Act modified (21.5.2020) by The Lake Lothing (Lowestoft) Third Crossing Order 2020 (S.I. 2020/474), art. 39(3) (with arts. 51, 57)
- C287Act applied (with modifications) (1.1.2022) by The Norfolk Boreas Offshore Wind Farm Order 2021 (S.I. 2021/1414), art. 1, Sch. 7 para. 3 (with arts. 41, 42, Sch. 17 para. 66)
- F91Words in s. 38(1) omitted (22.9.2017) by virtue of Neighbourhood Planning Act 2017 (c. 20), ss. 33(2), 46(1); S.I. 2017/936, reg. 3(c)
- C288Act applied (with modifications) (7.9.2023) by The A38 Derby Junctions Development Consent Order 2023 (S.I. 2023/923), art. 1, Sch. 6 paras. 1, 2 (with arts. 4, 45, Sch. 9 paras. 6, 46, 54(1))
- C289Act modified (30.4.2020) by The A585 Windy Harbour to Skippool Highway Development Consent Order 2020 (S.I. 2020/402), art. 1, Sch. 6 para. 2 (with arts. 5, 44)
- F92Word in s. 6D(3) substituted (31.1.2024) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 188(1)(a), 255(7) (with s. 247); S.I. 2024/92, reg. 2(o)
- C290Act applied (15.4.2025) by The A122 (Lower Thames Crossing) Development Consent Order 2025 (S.I. 2025/462), arts. 1, 42(3) (with arts. 5, 43, 53(7), Sch. 14)
- F93S. 18(2)(b)(iia) inserted (31.1.2025) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 189(4)(a)(ii), 255(7) (with s. 247); S.I. 2024/92, reg. 5 (with reg. 6(3)-(5))
- C291Pt. 1 applied (5.12.2022) by The Portishead Branch Line (MetroWest Phase 1) Order 2022 (S.I. 2022/1194), arts. 1, 14(4), 15(7), 20(6), 21(4), 23(5), 28(4), 32(4), 33(6), 34(8), 43(9), 44(3) (with arts. 32(5), 51)
- F94S. 4(6) omitted (1.6.2009) by virtue of The Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307), art. 1, Sch. 1 para. 39(c) (with Sch. 5)
- C292Act modified (13.11.2012) by The Chiltern Railways (Bicester to Oxford Improvements) Order 2012 (S.I. 2012/2679), art. 33 (with art. 42(2))
- C293S. 5 applied (1.4.2010) by The Conservation of Habitats and Species Regulations 2010 (S.I. 2010/490), regs. 1(2), 32(4) (with reg. 125)
- C294Pt. 1 applied (12.10.2025) by The Gatwick Airport (Northern Runway Project) Development Consent Order 2025 (S.I. 2025/1054), arts. 1, 13(4), 14(7), 23(10), 24(5), 25(3), 31(4), 35(4), 36(6), 38(9) (with arts. 5, 9(6), 23(9), 31(5), 35(5), 36(8)(11), 38(10), 43, Sch. 9)
- C295Act applied (22.10.2025) by The A46 Newark Bypass Development Consent Order 2025 (S.I. 2025/1090), arts. 1, 33(3) (with arts. 4, 9, 51, Sch. 9)
- C296S. 5 applied (with modifications) (16.3.2026) by Infrastructure (Wales) Act 2024 (asc 3), s. 147(2), Sch. 2 para. 9(1) (with s. 84(5)); S.I. 2025/1306, art. 2(h)
- C297Act modified (2.9.2022) by The A47 North Tuddenham to Easton Development Consent Order 2022 (S.I. 2022/911), art. 1, Sch. 6 para. 2 (with arts. 4, 53)
- C298Act applied (4.10.2024) by The National Grid (Bramford to Twinstead Reinforcement) Order 2024 (S.I. 2024/958), arts. 1, 30(3) (with art. 40, Sch. 14)
- C299Act applied (24.11.2016) by The Transport for Greater Manchester (Light Rapid Transit System) (Trafford Park Extension) Order 2016 (S.I. 2016/1035), art. 38(4) (with arts. 43, 44)
- C300Act modified (27.2.2020) by The A30 Chiverton to Carland Cross Development Consent Order 2020 (S.I. 2020/121), Sch. 6 para. 2 (with art. 3(1))
- C301S. 4 applied (with modifications) (6.4.2010) by The Environmental Permitting (England and Wales) Regulations 2010 (S.I. 2010/675), reg. 1(1)(b), Sch. 5 para. 7 (with reg. 1(2), Sch. 4)
- C302S. 5 applied (with modifications) (1.3.2009) by Environmental Damage (Prevention and Remediation) Regulations 2009 (S.I. 2009/153), reg. 1(1), Sch. 6 para. 6(1)
- F95Sch. 3 omitted (22.9.2017) by virtue of Neighbourhood Planning Act 2017 (c. 20), ss. 33(1)(b), 46(1); S.I. 2017/936, reg. 3(c)
- C303Act modified (22.8.2013) by The Leeds Railway Station (Southern Entrance) Order 2013 (S.I. 2013/1933), art. 30(3)
- C304Pt. 1 applied (9.5.2024) by The Sheringham Shoal and Dudgeon Extensions Offshore Wind Farm Order 2024 (S.I. 2024/564), arts. 1, 10(6), 15(10), 16(6), 20(4), 24(4), 25(6), 26(7), 33(3), 34(4) (with arts. 20(5), 24(5), 25(7), 26(8), 35, 36, Sch. 14)
- C305Pt. 1 applied (15.4.2025) by The A122 (Lower Thames Crossing) Development Consent Order 2025 (S.I. 2025/462), arts. 1, 12(6), 13(3), 14(6), 18(4), 20(11), 21(5), 23(3), 24(5), 29(5), 34(4), 35(7), 36(8) (with arts. 5, 29(6), 34(5), 35(9), 36(9), 43, 53(7), Sch. 14)
- C306Act applied (with modifications) (3.11.2022) by The Network Rail (Huddersfield to Westtown (Dewsbury) Improvements) Order 2022 (S.I. 2022/1067), art. 1, Sch. 12 paras. 1, 2 (with art. 46(2), Sch. 19 para. 61)
- C307Act applied (with modifications) (3.8.2024) by The Sunnica Energy Farm Order 2024 (S.I. 2024/802), art. 1, Sch. 9 paras. 1, 3 (with art. 44, Sch. 12)
- C308Act modified (25.2.2026) by The A46 Coventry Junctions (Walsgrave) Development Consent Order 2026 (S.I. 2026/125), arts. 1, 33(3) (with arts. 40, 45, Sch. 9)
- C309Act applied (with modifications) (4.3.2020) by The Midland Metro (Birmingham Eastside Extension) Order 2020 (S.I. 2020/141), Sch. 5 para. 2 (with arts. 47, 48, Sch. 10 para. 19)
- C310Act applied (with modifications) by 1981 c. 66, s. 7(1) (as substituted (3.2.2017) by Housing and Planning Act 2016 (c. 22), s. 216(3), Sch. 18 para. 3; S.I. 2017/75, reg. 3(k) (with reg. 5))
- C311Act applied (with modifications) (11.1.2023) by The Network Rail (Cambridge South Infrastructure Enhancements) Order 2022 (S.I. 2022/1406), art. 1, Sch. 10 paras. 1, 2 (with art. 34(2), Sch. 12 paras. 5, 47, 79)
- F96Words in s. 35 substituted (1.6.2009) by The Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307), art. 1, Sch. 1 para. 44 (with Sch. 5)
- C312Pt. 1 applied (15.2.2025) by The West Burton Solar Project Order 2025 (S.I. 2025/116), arts. 1, 11(5), 12(3), 17(9), 18(5), 23(4), 28(4), 29(7), 30(7), 38(4), 39(4) (with arts. 23(5), 28(5), 29(8)(11)(13), 30(8), 47, Sch. 15)
- C313S. 12 applied (with modifications) (16.3.2026) by Infrastructure (Wales) Act 2024 (asc 3), s. 147(2), Sch. 2 para. 8(8) (with s. 84(5)); S.I. 2025/1306, art. 2(h)
- C314Act applied (with modifications) (5.12.2022) by The Portishead Branch Line (MetroWest Phase 1) Order 2022 (S.I. 2022/1194), art. 1, Sch. 11 para. 2 (with art. 51)
- C315Act applied (6.6.2022) by The M25 Junction 28 Development Consent Order 2022 (S.I. 2022/573), arts. 1, 51, Sch. 7 para. 2 (with arts. 5, 36)
- C316Pt. 1 applied (10.3.2023) by The A47 Wansford to Sutton Development Consent Order 2023 (S.I. 2023/218), arts. 1, 16(5), 17(7), 22(10), 23(5), 29(5), 33(4), 34(6), 35(8), 39(3), 40(4) (with arts. 4, 29(6), 33(5), 34(8), 35(9), 37, 50)
- C317S. 5A applied (with modifications) (11.2.2021) by 2017 c. 7, Sch. 9 paras. 1, 2(8B) (as substituted by High Speed Rail (West Midlands - Crewe) Act 2021 (c. 2), s. 64(1), Sch. 9 para. 5)
- C318Act modified (11.3.2014) by The Crossrail (Paddington Station Bakerloo Line Connection) Order 2014 (S.I. 2014/310), art. 15
- C319Pt. 1 applied (22.12.2021) by The Morlais Demonstration Zone Order 2021 (S.I. 2021/1478), arts. 1, 8(6), 11(3), 13(10), 14(13)(14), 27(3)(5), 28(6)(7), 29(7), 31(2), 35(4)(5), 40(3), Sch. 10 para. 2 (with arts. 15, 50, Sch. 11 para. 29)
- C320Pt. 1 applied (22.4.2022) by The East Anglia TWO Offshore Wind Farm Order 2022 (S.I. 2022/433), arts. 1(2), 10(3), 11(4), 12(6), 17(6), 21(4)(8), 25(4), 26(6), 27(7), 34(2)(4) (with arts. 21(5), 25(5), 26(7), 27(8), 40, 41)
- F97S. 6E(3A) inserted (31.1.2024) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 188(2)(d), 255(7) (with s. 247); S.I. 2024/92, reg. 2(o)
- F98S. 17(1A)-(1C) inserted (31.1.2025) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 189(3)(b), 255(7) (with s. 247); S.I. 2024/92, reg. 5 (with reg. 6(3)-(5))
- C321Act modified (15.9.2016) by The River Humber Gas Pipeline Replacement Order 2016 (S.I. 2016/853), art. 30(3) (with art. 43)
- C322S. 6A modified by 1999 c. 29, ss. 403A(9), 403B(9) (as inserted (22.9.2017) by Neighbourhood Planning Act 2017 (c. 20), ss. 36(2), 46(1); S.I. 2017/936, reg. 3(f))
- F99Words in s. 4(3) substituted (1.6.2009) by The Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307), art. 1, Sch. 1 para. 39(b) (with Sch. 5)
- C323S. 5A(5A) modified (23.9.2020) by The Midland Metro (Wednesbury to Brierley Hill Land Acquisition) Order 2020 (S.I. 2020/1067), Sch. 2 para. 2
- F100Words in s. 31(6) substituted (1.6.2009) by The Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307), art. 1, Sch. 1 para. 43 (with Sch. 5)
- F101S. 4A inserted (6.4.2018) by Housing and Planning Act 2016 (c. 22), ss. 192(1), 216(3); S.I. 2018/251, reg. 4(c)
- C324Act applied (with modifications) (26.9.2018) by The Network Rail (Felixstowe Branch Line Improvements Level Crossings Closure) Order 2018 (S.I. 2018/937), Sch. 8 para. 2
- F102Words in s. 17(1) substituted (31.1.2025) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 189(3)(a), 255(7) (with s. 247); S.I. 2024/92, reg. 5 (with reg. 6(3)-(5))
- C325Act modified (21.4.2015) by The Crossrail (Plumstead Sidings) Order 2015 (S.I. 2015/781), art. 14(3)
- C326Pt. 1 applied (3.8.2024) by The Sunnica Energy Farm Order 2024 (S.I. 2024/802), arts. 1, 11(5), 15(10), 16(6), 20(4), 25(4), 26(8), 27(7), 35(3), 36(4) (with arts. 25(5), 26(9)(12), 27(8), 44, Sch. 12)
- C327Pt. 1 applied (14.6.2024) by The A1 in Northumberland: Morpeth to Ellingham Development Consent Order 2024 (S.I. 2024/733), arts. 1, 16(6), 17(6), 23(2), 25(10), 26(5), 31(6), 35(4), 36(6), 37(8), 41(3), 42(4) (with arts. 6, 25(9), 31(6), 35(5), 36(8), 37(9), Sch. 10)
- C328Act modified (1.9.2020) by The Immingham Open Cycle Gas Turbine Order 2020 (S.I. 2020/847), Sch. 7 para. 3 (with Sch. 9 para. 144)
- F103Words in s. 4(4) substituted (1.6.2009) by The Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307), art. 1, Sch. 1 para. 39(b) (with Sch. 5)
- C329S. 4 applied (with modifications) (1.1.2017) by The Environmental Permitting (England and Wales) Regulations 2016 (S.I. 2016/1154), reg. 1(1), Sch. 5 para. 7(4) (with regs. 1(3), 77-79, Sch. 4)
- F104Words in s. 31(2) substituted (1.6.2009) by The Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307), art. 1, Sch. 1 para. 43 (with Sch. 5)
- C330Pt. 1 applied (1.8.2022) by The Northumberland Line Order 2022 (S.I. 2022/820), arts. 1, 4(6), 6(3), 7(4), 8(6), 9(6), 19(6), 20(5), 23(5) (with Sch. 10 paras. 21, 43)
- C331S. 4 applied (with modifications) by S.I. 2006/2989, Sch 2 para. 6(4) (as substituted (W.) (6.4.2012) by The Contaminated Land (Wales) (Amendment) Regulations 2012 (No. 283), regs. 1(1), 2(4)(c))
- C332S. 4 applied (with modifications) (13.7.2016) by Housing and Planning Act 2016 (c. 22), ss. 176(3), 216(3); S.I. 2016/733, reg. 3(h)
- C333Act applied (with modifications) (28.7.2025) by The Mona Offshore Wind Farm Order 2025 (S.I. 2025/870), art. 1, Sch. 9 paras. 1, 2 (with arts. 37, 38, Sch. 10)
- C334S. 5 modified (E.) (19.7.2015) by The Environmental Damage (Prevention and Remediation) (England) Regulations 2015 (S.I. 2015/810), reg. 1(1), Sch. 6 para. 6(1) (with regs. 4-8)
- C335Act applied (with modifications) (25.6.2025) by The M5 Junction 10 Development Consent Order 2025 (S.I. 2025/795), art. 1, Sch. 6 paras. 1, 2 (with arts. 4, 43, Sch. 9)
- C336Act modified (10.10.2019) by The Abergelli Power Gas Fired Generating Station Order 2019 (S.I. 2019/1268), art. 1, Sch. 8 para. 3
- C337Act modified (7.8.2015) by The Preesall Underground Gas Storage Facility Order 2015 (S.I. 2015/1561), art. 26(3) (with art. 44)
- C338Act applied (25.10.2024) by The Associated British Ports (Immingham Eastern Ro-Ro Terminal) Development Consent Order 2024 (S.I. 2024/1014), arts. 1, 19(3) (with arts. 12(4), 27(9), 36, 40, Sch. 4)
- C339S. 5(5A) modified (6.8.2020) by The A19 Downhill Lane Junction Development Consent Order 2020 (S.I. 2020/746), art. 1, Sch. 5 para. 2 (with art. 5)
- C340Act modified (1.9.2021) by The Network Rail (Teddington Station Access for All) Order 2021 (S.I. 2021/937), arts. 1, 13(3), Sch. 5 para. 2
- C341Pt. 1 applied (8.9.2022) by The Manston Airport Development Consent Order 2022 (S.I. 2022/922), arts. 1, 12(5), 13(5), 17(10), 18(5), 24(5), 28(4), 29(6), 30(7), 34(3) (with arts. 5, 24(6), 28(5), 29(8), 30(8), 32, 40)
- C342Act modified (9.6.2009) by Nottingham Express Transit System Order 2009 (S.I. 2009/1300), art. 39 (with Sch. 13 para. 14(2), Sch. 14 para. 19)
- C343Pt. 1 applied (30.9.2025) by The M60/M62/M66 Simister Island Interchange Development Consent Order 2025 (S.I. 2025/1018), arts. 1, 14(5), 16(4), 19(11), 20(5), 25(5), 29(4), 30(6), 31(9), 36(4) (with arts. 5, 19(9), 25(6), 29(5), 30(8), 31(10), 34, Sch. 9)
- C344Pt. 1 applied (2.8.2022) by The Network Rail (Oxford Station Phase 2 Improvements (Land Only)) (No. 2) Order 2022 (S.I. 2022/872), arts. 1, 8(7), 9(7), 12(5), 14(3), 15(3), 16(14) (with art. 12(6))
- C345Act applied (with modifications) (30.6.2022) by The Network Rail (Essex and Others Level Crossing Reduction) Order 2022 (S.I. 2022/651), art. 1, Sch. 12 paras. 1, 2
- C346S. 32 applied (30.10.2019) by The Northampton Gateway Rail Freight Interchange Order 2019 (S.I. 2019/1358), art. 1, Sch. 13 Pt. 2 para. 5(6) (with Sch. 13 Pt. 1 para. 19)
- F105Words in s. 4(5) substituted (1.6.2009) by The Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307), art. 1, Sch. 1 para. 39(b) (with Sch. 5)
- F106S. 22(2A) inserted (31.1.2025) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 189(7), 255(7) (with s. 247); S.I. 2024/92, reg. 5 (with reg. 6(3)-(5))
- C347Pt. 1 applied (9.10.2024) by Development The M3 Junction 9 Consent Order 2024 (S.I. 2024/752), arts. 1, 16(5), 17(4), 22(10), 23(5), 29(5), 33(4), 34(6), 35(7), 39(3), 40(4) (with arts. 4, 29(6), 33(5), 34(7), 35(8), 37, Sch. 10) (as amended by S.I. 2024/1020, Sch.)Pt. 1 applied (25.10.2024) by The Associated British Ports (Immingham Eastern Ro-Ro Terminal) Development Consent Order 2024 (S.I. 2024/1014), arts. 1, 12(3), 26(5), 27(10) (with arts. 12(4), 27(9), 36, 40, Sch. 4)
- C348Act applied (with modifications) (4.4.2025) by The North Lincolnshire Green Energy Park Order 2025 (S.I. 2025/362), art. 1, Sch. 11 paras. 1, 3 (with Sch. 14)
- C349Act modified (1.2.2011) by The River Mersey (Mersey Gateway Bridge) Order 2011 (S.I. 2011/41), art. 31 (with art. 51, Sch. 10 paras. 68, 85)
- C350Act applied (with modifications) (23.4.2025) by The Cambridge Waste Water Treatment Plant Relocation Order 2025 (S.I. 2025/452), art. 1, Sch. 13 paras. 1, 3 (with art. 50)
- C351Act modified (24.11.2016) by The Transport for Greater Manchester (Light Rapid Transit System) (Trafford Park Extension) Order 2016 (S.I. 2016/1035), art. 36(3) (with arts. 43, 44)
- C352Act modified (28.9.2004 for E., 15.10.2005 for W.) by Planning and Compulsory Purchase Act 2004 (c. 5), s. 38 (with s. 111); S.I. 2004/2202, art. 2(c); S.I. 2005/2847, art. 2(a) (with art. 3(1)(2))
- C353S. 4 applied (18.2.2026) by Planning and Infrastructure Act 2025 (c. 34), ss. 86(4), 118(3) (with ss. 98, 116); S.I. 2025/1370, reg. 4(1)(l)
- C354S. 31 excluded (21.11.2013) by The Network Rail (Redditch Branch Enhancement) Order 2013 (S.I. 2013/2809), arts. 1, 9(6) (with arts. 27(2), 39, Sch. 10 para. 4)
- C355Act modified (28.3.2024) by The A66 Northern Trans-Pennine Development Consent Order 2024 (S.I. 2024/360), arts. 1, 38(3) (with arts. 18, 35, Sch. 9)
- C356Act excluded (W.) (4.11.2024) by Historic Environment (Wales) Act 2023 (asc 3), ss. 140(4)(a), 212(2) (with Sch. 14 paras. 1-3); S.I. 2024/860, art. 3(b)
- C357Act applied (with modifications) (1.5.2025) by The Viking CCS Carbon Dioxide Pipeline Order 2025 (S.I. 2025/509), art. 1(2), Sch. 8 paras. 1, 2 (with art. 41, Sch. 9)
- C358S. 5 applied (1.1.2017) by The Environmental Permitting (England and Wales) Regulations 2016 (S.I. 2016/1154), reg. 1(1), Sch. 5 para. 6(2) (with regs. 1(3), 77-79, Sch. 4)
- C359S. 4(1)(a) applied (with modifications) by 1985 c. 68, s. 584B(6) (as substituted (6.4.2006 for E., 16.6.2006 for W.) by Housing Act 2004 (c. 34), s. 270(4)(5)(f), Sch. 15 para. 31; S.I. 2006/1060, art. 2(1)(d) (with Sch.); S.I. 2006/1535, art. 2(b) (with Sch.))
- C360Pt. 1 applied (4.3.2026) by The Outer Dowsing Offshore Wind Farm Order 2026 (S.I. 2026/138), arts. 1(2), 10(7), 11(6), 17(6), 21, 25, 26, 27, 35(3), 36(5) (with arts. 42, 43, Sch. 18)
- C361Pt. 1 applied (with modifications) by Agriculture (Miscellaneous Provisions) Act 1968 (c. 34), s. 13(3), Sch. 3 paras. 4, 5Pt. 1 applied by Channel Tunnel Act 1987 (c. 53, SIF 102), ss. 6, 35, Sch. 2 paras. 4(3), 7(3), 13(9), 14(8), 16(8), Sch. 4 para. 4(5), Sch. 5 Pt. 3 para. 6(2)Pt. 1 applied by Dartford-Thurrock Crossing Act 1988 (c. 20, SIF 59), ss. 2(5), 3, Sch. 2 Pt. 2 para. 5(2), Sch. 3 paras 1(9), 2(5)Pt. 1 applied (13.2.1992) by Severn Bridges Act 1992 (c. 3), ss. 2(6), 3, Sch. 2 Pt. 2 para. 4(2), Pt. 3 para. 7(7)(8), Sch. 3 para. 1(6)Pt. 1 applied (21.7.1994) by 1994 c. xi, ss. 19(3), 20(4), 23(7), 29(3), 34(6), 41(3) (with s. 39)Pt. 1 applied (21.7.1994) by 1994 c. xv, ss. 10(2)(b), 22(g), 27(3), 34(7), 61(2)(3) (with s. 47)Pt. 1 applied (11.11.1996) by S.I. 1996/2714, arts. 10(4), 18(6), 21(5), 28(3), 29(6), 32(4), 40(4)Pt. 1 applied (18.12.1996) by 1996 c. 61, ss. 2, 3, 6, 7(4)(5), 44, Sch. 2 paras. 8(2)(3), 10(8), Sch. 3 para. 3(3), Sch. 5 paras. 1(5)(6), 4(7)(8), 5(3), Sch. 12 Pt. 2, para. 3(6)Pt. 1 applied (10.2.1997) by S.I. 1997/264, arts. 7(4), 14(10), 15(5), 16(6), 20(3), 24(3)Pt. 1 applied (21.5.1997) by S.I. 1997/1266, arts. 11(5), 19(6), 21(5), 30(6), 33(4) (with art. 41)Pt. 1 applied (27.8.1998) by S.I. 1998/1936, arts. 11(6), 19(6), 21(1), 32(6), 33(7), 36(4) (with art. 45)Pt. 1 applied (13.1.1999) by S.I. 1998/3269, arts. 9(5), 16(7), 18(4), 27(3)Pt. 1 applied (19.2.1999) by S.I. 1999/537, art. 10(6)Pt. 1 applied (30.4.1999) by S.I. 1999/1306, arts. 1, 12(5), 14(6), 15(7), 21(3)Pt. 1 applied (18.5.1999) by S.I. 1999/1664, arts. 8(4), 9(6), 10(7) (with art. 18)Pt. 1 applied (20.8.1999) by S.I. 1999/2336, arts. 8(3), 9(7), 17(6), 20(3)Pt. 1 applied (23.8.1999) by S.I. 1999/2981, arts. 6(5), 13(10), 14(5), 20(6), 21(7), 24(3), 25(2), 27Pt. 1 applied (3.6.1999) by S.I. 1999/1555, art. 7(2)Pt. 1 applied (24.12.1999) by S.I. 2000/428, art. 8(4)Pt. 1 applied (29.3.2001) by S.I. 2001/1347, arts. 11(6), 19(10), 21(5), 27(3), 28(6), 29(7), 32(3) (with arts. 15, 37, 38(2))Pt. 1 applied (2.3.2001) by S.I. 2001/1368, arts. 10(3), 13(4)Pt. 1 applied (2.3.2001) by S.I. 2001/1369, arts. 8(3), 11(4)Pt. 1 applied (18.7.2001) by S.I. 2001/2870, art. 10(7)Pt. 1 applied (24.7.2001) by S.I. 2001/3627, arts. 11(6), 27(6), 29(10), 32(5), 40(3), 41(6), 42(7)(8), 45(4), 55(3)(4)Pt. 1 applied (9.11.2001) by S.I. 2001/3682, arts. 7(4)(5), 15(10), 16(5), 22(3), 26(3)(4) (with Sch. 12 para. 2)Pt. 1 applied (30.4.2002) by S.I. 2002/1065, arts. 7(11), 8(4), 14(6), 15(7), 19(3)Pt. 1 applied (12.8.2002) by S.I. 2002/1943, arts. 8(4), 9(7) (with art. 9(8)(9))Pt. 1 applied (31.5.2002) by S.I. 2002/1327, arts. 10(2) (subject to Sch. 2, para. 5), 15(5), 26(4)Pt. 1 applied (14.3.2002) by S.I. 2002/412, arts. 13(5), 19(3), 22(2), 28(3), (with saving in art. 38)Pt. 1 applied (31.12.2002) by S.I. 2002/3127, art. 7(3) (with arts. 16, 17)Pt. 1 applied (28.4.2003) by Network Rail (West Coast Main Line) Order 2003 (S.I. 2003/1075), arts. 1, 7(4), 9(2), 13(8), 30(6) (with art. 40)Pt. 1 applied (4.3.2004) by The Network Rail (West Coast Main Line) Order 2004 (S.I. 2004/389), arts. 1, 7(4), 8(5), 9(5), 11(2), 12(8), 20(10), 21(5), 27(3), 28(7), 31(3) (with art. 38)Pt. 1 applied (2.4.2004) by Docklands Light Railway (Woolwich Arsenal Extension) Order 2004 (S.I. 2004/757), arts. 1, 10(6), 19(10), 21(5), 29(3), 30(8) (with arts. 30(9), 31(7), 32(5), 35(4)(5), Sch. 12 para. 2)Pt. 1 applied (19.11.2004) by Scarweather Sands Offshore Wind Farm Order 2004 (S.I. 2004/3054), arts. 1, 6(6), 7(5), 21(5)(6) (with art. 38)Pt. 1 applied (28.1.2005) by East Midlands Parkway Station (Land Acquisition) Order 2005 (S.I. 2005/8), arts. 1, 9(3)Pt. 1 applied (11.2.2005) by Merseytram (Liverpool City Centre to Kirkby) Order 2005 (S.I. 2005/120), arts. 1, 11(6), 19(8), 22(10), 25(5), 35(3), 36(6), 37(7), 40(4), 71(8) (with arts. 65, 66)Pt. 1 applied (22.3.2005) by Midland Metro (Wednesbury to Brierley Hill and Miscellaneous Amendments) Order 2005 (S.I. 2005/927), arts. 12, 13(6), 21(6), 23(6), 24(10), 26(5), 28(3), 33(3)(4), 34(6), 35(7), 36(8), 39(3), Sch. 10 para. 2 (with arts. 23(7), 24(9), 34(7), 35(8), 39(4)(8), 51)Pt. 1 applied (4.5.2005) by The Telford Railfreight Terminal (Donnington) Order 2005 (S.I. 2005/1163), arts. 1, 9(5), 10(6), 12(8), 18(2)Pt. 1 applied (22.7.2005) by Midland Metro (Birmingham City Centre Extension, etc.) Order 2005 (S.I. 2005/1794), arts. 1, 12(2), 20(6), 21(10), 23(5), 29(3), 30(6), 31(7), 32(7), 35(3) (with arts. 21(11), 29(4), 30(7), 31(8), 35(4), 35(8), 47)Pt. 1 applied (3.8.2005) by The Greater Manchester (Leigh Busway) Order 2005 (S.I. 2005/1918), arts. 1, 41(4)Pt. 1 applied (26.8.2005) by River Tyne (Tunnels) Order 2005 (S.I. 2005/2222), arts. 1, 14(10), 16(5), 27(6), 28(7), 31(4), 32(3) (with arts. 45(1), 48, Sch. 10 paras. 21, 29)Pt. 1 applied (8.10.2005) by Leicestershire County Council (Ashby de la Zouch Canal Extension) Order 2005 (S.I. 2005/2786), arts. 1, 15(4)(5), 19(6)(7), 22Pt. 1 applied (25.11.2005) by Docklands Light Railway (Capacity Enhancement) Order 2005 (S.I. 2005/3105), arts. 1, 12(7), 20(10), 22(5), 29, 30(6), 31(7), 34(4), 38(4) (with arts. 3(5), 15(3))Pt. 1 applied (11.1.2006) by The Cambridgeshire Guided Busway Order 2005 (S.I. 2005/3523), arts. 1, 10(4), 19(5), 27(3), 28(6), 29(7), 32(4), 43(3) (with arts. 19(6), 28(7), 52)Pt. 1 applied (3.7.2006) by Port of Blyth (Battleship Wharf Railway) Order 2006 (S.I. 2006/1518), arts. 1, 9(4)Pt. 1 applied (14.9.2006) by The Borough of Poole (Poole Harbour Opening Bridges) Order 2006 (S.I. 2006/2310), arts. 1, 5(6), 8(4), 15(10), 16(5), 23(6), 24(7), 27, 28(2) (with arts. 23(7), 24(8), 28(3), 40, Sch. 7 para. 12)Pt. 1 applied (22.11.2006) by Docklands Light Railway (Stratford International Extension) Order 2006 (S.I. 2006/2905), arts. 1, 10(6), 11(6), 16(10), 18(5), 26(3), 27(6), 28(7), 31(4), 34(4) (with arts. 27(7), 28(8), 31(5), 43)Pt. 1 applied (13.12.2006) by Luton Dunstable Translink Order 2006 (S.I. 2006/3118), arts. 1, 9(6), 10(7), 16(10), 17(5), 23(3), 24(6), 27(3), 33(3)Pt. 1 applied (13.12.2006) by The Network Rail (Thameslink 2000) Order 2006 (S.I. 2006/3117), arts. 1, 15(8), 16(8), 22(10), 23(5), 28(3), 29(6), 32(3) (with arts. 34, 35(2))Pt. 1 applied (19.3.2007) by Ouseburn Barrage Order 2007 (S.I. 2007/608), arts. 1, 6(3)(4), 7(4)(5), 28(7), 31(4) (with arts. 46-48, Sch. 5 para. 2, Sch. 6 para. 23)Pt. 1 applied (23.8.2007) by Docklands Light Railway (Capacity Enhancement and 2012 Games Preparation) Order 2007 (S.I. 2007/2297), arts. 1, 9(6), 10(6), 14(5), 16(10), 18(5), 25(3), 26(6), 27(7), 30(4), 32(4) (with arts. 3(6), 12(3))Pt. 1 applied (28.9.2007) by London Gateway Logistics and Commercial Centre Order 2007 (S.I. 2007/2657), arts. 1, 12(3) (with arts. 19, 28, Sch. 3 para. 13(2))Pt. 1 applied (17.12.2007) by Felixstowe Dock and Railway Company (Land Acquisition) Order 2007 (S.I. 2007/3345), arts. 1(1), 7(2)Pt. 1 applied (16.5.2008) by London Gateway Port Harbour Empowerment Order 2008 (S.I. 2008/1261), arts. 1, 22(5), 32(2) (with arts. 41(1), 45, 54(2), 55, 56, 57, 58(6))Pt. 1 applied (21.5.2008) by Teesport (Land Acquisition) Order 2008 (S.I. 2008/1238), arts. 1(1), 6(6), 8(4)Pt. 1 applied (22.7.2008) by Crossrail Act 2008 (c. 18), s. 8(8), Sch. 2 paras. 7(2), 9(8), 10(6), Sch. 3 para. 3(3), Sch. 5 paras. 1(5), 3(3), 4(7), 5(4)Pt. 1 applied (14.10.2008) by Felixstowe Branch Line and Ipswich Yard Improvement Order 2008 (S.I. 2008/2512), arts. 1, 8(6), 10(6), 17(6), 18(3), 20(10), 21(5), 26, 27(6), 28(7), 32(4), 35(3) (with arts. 21(6), 32(5), 36(3))Pt. 1 applied (29.12.2008) by Network Rail (Thameslink) (Land Acquisition) Order 2008 (S.I. 2008/3163), arts. 1, 12(3)Pt. 1 applied (9.6.2009) by Nottingham Express Transit System Order 2009 (S.I. 2009/1300), arts. 1, 11(6), 12(6), 20(5), 22(10), 25(5), 35(3)(5), 36(6), 37(7), 41(4), 51(3), 76(8) (with arts. 25(6), 37(8), 41(5), 45(2), 51(3), Sch. 13 para. 14(2), Sch. 14 para. 19, Sch. 16)Pt. 1 applied (18.9.2009) by London Underground (Victoria Station Upgrade) Order 2009 (S.I. 2009/2364), arts. 1, 8(3), 9(8), 14(10), 16(5), 23(3), 24(6), 25(7), 29(4), 35(7)Pt. 1 applied (28.10.2009) by Network Rail (Reading) (Land Acquisition) Order 2009 (S.I. 2009/2728), arts. 1, 9(3), 10(6), 11(3), 12(7), 16(4)Pt. 1 applied (20.7.2010) by The Network Rail (Nuneaton North Chord) Order 2010 (S.I. 2010/1721), arts. 1, 20(7), 24(3), 27(3)Pt. 1 applied (27.8.2010) by The Llangollen and Corwen Railway Order 2010 (S.I. 2010/2136), arts. 1(1), 8(5), 12(3)Pt. 1 applied (1.2.2011) by The River Mersey (Mersey Gateway Bridge) Order 2011 (S.I. 2011/41), arts. 1, 8(6), 9(6), 15(10), 16(5), 17(4), 25(3), 28(6), 29(7), 33(4), 48(3) (with art. 51, Sch. 10 paras. 68, 85)Pt. 1 applied (21.4.2011) by The Network Rail (Hitchin (Cambridge Junction)) Order 2011 (S.I. 2011/1072), arts. 1, 9(4), 10(6), 15(5), 23(3), 24(7), 25(7), 29(4), 32(3)Pt. 1 applied (7.8.2012) by The Ipswich Barrier Order 2012 (S.I. 2012/1867), arts. 1, 6(8), 7(5), 27(6), 28(7), 32(4) (with arts. 46-48, Sch. 8 para. 18)Pt. 1 applied (12.8.2012) by The Hinkley Point (Temporary Jetty) (Land Acquisition) Order 2012 (S.I. 2012/1924), arts. 1, 9(3)Pt. 1 applied (16.8.2012) by The Hinkley Point Harbour Empowerment Order 2012 (S.I. 2012/1914), arts. 1(1), 19(5), 20(3) (with arts. 34, 35, 37, 40)Pt. 1 applied (26.9.2012) by The Network Rail (Ipswich Chord) Order 2012 (S.I. 2012/2284), arts. 1, 11(7), 13(10), 15(5), 19(5), 23(6)(7), 27(3) (with arts. 23(7), 26(2))Pt. 1 applied (6.11.2012) by The Network Rail (North Doncaster Chord) Order 2012 (S.I. 2012/2635), arts. 1, 13(4), 15(6), 19(4), 21(5), 25(5), 29(4)(5), 30(6), 36(3) (with art. 35(2))Pt. 1 applied (13.11.2012) by The Chiltern Railways (Bicester to Oxford Improvements) Order 2012 (S.I. 2012/2679), arts. 1, 9(6), 10(6), 15(4), 17(3), 20(10), 21(5), 28(3), 29(6), 30(7), 35(4), 40(3) (with art. 42(2))Pt. 1 applied (28.3.2013) by The Network Rail (Seaham Level Crossing) Order 2013 (S.I. 2013/533), arts. 1, 3(4), 8(6), 12(3)Pt. 1 applied (9.4.2013) by The Hinkley Point C (Nuclear Generating Station) Order 2013 (S.I. 2013/648), arts. 1, 15(8), 17(5), 22(10), 23(5), 28(4), 32(4), 33(6), 34(7), 41(3), 42(4) (with arts. 28(5), 33(7)(11), 34(8), 48, 68, 79)Pt. 1 applied (15.6.2013) by The Galloper Wind Farm Order 2013 (S.I. 2013/1203), arts. 1, 15(5), 19(5), 22(4), 23(7), 24(7) (with arts. 11, 12)Pt. 1 applied (15.8.2013) by The North Blyth Biomass Power Station Order 2013 (S.I. 2013/1873), arts. 1, 12(5), 13(3), 16(4), 17(3) (with arts. 17(4), 30)Pt. 1 applied (22.8.2013) by The Leeds Railway Station (Southern Entrance) Order 2013 (S.I. 2013/1933), arts. 1, 8(3), 9(5), 14(10), 15(5), 16(4), 26(3), 27(7), 28(7), 32(4), 35(3)Pt. 1 applied (6.11.2013) by The Transport for Greater Manchester (Light Rapid Transit System) (Second City Crossing) Order 2013 (S.I. 2013/2587), arts. 1, 13(6), 19(7), 21(10), 23(5), 31(3), 32(6), 33(7), 37(4) (with arts. 31(5), 32(7), 33(8), 38(2), 42, 43)Pt. 1 applied (20.11.2013) by The M1 Junction 10a (Grade Separation) Order 2013 (S.I. 2013/2808), arts. 1, 17(5), 25(6), 30(3), 31(4)Pt. 1 applied (21.11.2013) by The Network Rail (Redditch Branch Enhancement) Order 2013 (S.I. 2013/2809), arts. 1, 14(5), 18(5), 24(7), 28(3) (with arts. 24(8), 27(2), 39, Sch. 10 para. 4)Pt. 1 applied (with modifications) (21.11.2013) by The Network Rail (Redditch Branch Enhancement) Order 2013 (S.I. 2013/2809), arts. 1, 23(6) (with arts. 16(2), 23(7), 27(2), 39, Sch. 10 para. 4)Pt. 1 applied (9.1.2014) by The Ashton Vale to Temple Meads and Bristol City Centre Rapid Transit Order 2013 (S.I. 2013/3244), arts. 1, 10(7), 11(6), 16(5), 18(10), 20(5), 27(3), 28(7), 29(7), 33(4), 41(3) (with arts. 57, 58, Sch. 9 para. 2, Sch. 11 para. 19)Pt. 1 applied (9.1.2014) by The National Grid (King’s Lynn B Power Station Connection) Order 2013 (S.I. 2013/3200), arts. 1, 16(10), 17(5), 18(4), 24(4), 25(7), 26(7), 30(3) (with arts. 16(9), 20(2), 24(5), 25(8), 26(8))Pt. 1 applied (11.3.2014) by The Crossrail (Paddington Station Bakerloo Line Connection) Order 2014 (S.I. 2014/310), arts. 1, 7(10), 13(6)Pt. 1 applied (21.4.2014) by The Network Rail (Norton Bridge Area Improvements) Order 2014 (S.I. 2014/909), arts. 1, 11(4), 13(5), 17(4), 19(5), 23(5), 27(5)(6), 28(6), 29(6), 30(7), 35(3) (with art. 34(2))Pt. 1 applied (7.5.2014) by The National Grid (North London Reinforcement Project) Order 2014 (S.I. 2014/1052), arts. 1, 12(4), 14(6), 18(10), 19(5), 20(7)(b), 26(5), 30(4), 31(6), 32(7), 37(3) (with art. 35)Pt. 1 applied (7.7.2014) by The East Anglia ONE Offshore Wind Farm Order 2014 (S.I. 2014/1599), arts. 1, 10(5), 18(4), 22(4), 23(6), 24(7), 32(3) (with arts. 23(7), 37, 38, Sch. 9 para. 19)Pt. 1 applied (24.7.2014) by The Daventry International Rail Freight Interchange Alteration Order 2014 (S.I. 2014/1796), arts. 1, 18(5), 22(4), 26(3) (with arts. 22(5), 24(2), 26(4)(5), Sch. 6 para. 3)Pt. 1 applied (29.7.2014) by The Felixstowe Branch Line (Land Acquisition) Order 2014 (S.I. 2014/1821), arts. 1, 7(3), 8(6), 9(7)Pt. 1 applied (19.8.2014) by The Network Rail (Huyton) Order 2014 (S.I. 2014/2027), arts. 1, 8(2), 14(10), 21(6), 22(7), 26(5), 30(3) (with arts. 21(7), 22(8), 26(6), 31(2))Pt. 1 applied (18.9.2014) by The A556 (Knutsford to Bowdon Improvement) Development Consent Order 2014 (S.I. 2014/2269), arts. 1, 11(6), 12(5), 16(10), 17(5), 21(5), 25(4), 26(6), 30(3) (with arts. 21(6), 28)Pt. 1 applied (24.9.2014) by The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 (S.I. 2014/2384), arts. 1, 13(5), 15(5), 20(10), 21(10), 22(7), 25(3), 26(4), 27(7), 28(3), 29(4), 35(7), 36(7)Pt. 1 applied (2.10.2014) by The North Killingholme (Generating Station) Order 2014 (S.I. 2014/2434), arts. 1, 10(6), 15(5), 16(3), 18(4), 20(4), 24(4), 25(6), 26(7), 31(3), 32(10) (with arts. 5, 6, 13, 16(4), 32(9), Sch. 8 Pt. 1 para. 6, Sch. 8 Pt. 3 paras. 4(3), 6, 17, Sch. 8 Pt. 5 para. 9)Pt. 1 excluded (2.10.2014) by The Clocaenog Forest Wind Farm Order 2014 (S.I. 2014/2441), arts. 1, 28(3) (with art. 33)Pt. 1 applied (2.10.2014) by The Clocaenog Forest Wind Farm Order 2014 (S.I. 2014/2441), arts. 1, 11(3), 14(5), 19(5), 24(3) (with art. 33)Pt. 1 applied (7.1.2015) by The Willington C Gas Pipeline Order 2014 (S.I. 2014/3328), arts. 1, 15(5), 16(3), 18(4), 20(4), 23(4), 24(6), 25(7), 32(3) (with art. 28(8))Pt. 1 applied (21.10.2014) by The Central Bedfordshire Council (Woodside Link Houghton Regis) Development Consent Order 2014 (S.I. 2014/2637), arts. 1, 12(6), 13(6), 17(10), 18(6), 22(5), 26(4), 27(6), 28(7), 33(3)Pt. 1 applied (23.10.2014) by The South Hook Combined Heat and Power Plant Order 2014 (S.I. 2014/2846), arts. 1, 11(5)Pt. 1 applied (15.12.2014) by The London Underground (Northern Line Extension) Order 2014 (S.I. 2014/3102), arts. 1, 10(6), 13(3), 18(10), 20(5), 21(3), 29(3), 30(8), 31(8), 35(4) (with arts. 18(9), 29(5), 30(9), 31(9), 35(5), Sch. 8 para. 45)Pt. 1 applied (31.12.2014) by The Hornsea One Offshore Wind Farm Order 2014 (S.I. 2014/3331), arts. 1, 8(6), 13(5), 16(6), 18(4), 22(4)(5), 23(7), 24(7), 27(5), 28(4) (with arts. 37, 38)Pt. 1 applied (2.2.2015) by The Northumberland County Council (A1 – South East Northumberland Link Road (Morpeth Northern Bypass)) Development Consent Order 2015 (S.I. 2015/23), arts. 1, 10(6), 19(5), 23(8), 24(5), 29(6), 30(7), 34(3) (with arts. 10(7), 24(6))Pt. 1 applied (with modifications) (2.2.2015) by The Northumberland County Council (A1 – South East Northumberland Link Road (Morpeth Northern Bypass)) Development Consent Order 2015 (S.I. 2015/23), arts. 1, 28(4)Pt. 1 applied (25.2.2015) by The A160/A180 (Port of Immingham Improvement) Development Consent Order 2015 (S.I. 2015/129), arts. 1, 12(6), 13(5), 17(10), 18(5), 23(5), 27(4)(5), 28(6), 29(7), 33(3) (with art. 31)Pt. 1 applied (26.2.2015) by The Cornwall Council (A30 Temple to Higher Carblake Improvement) Order 2015 (S.I. 2015/147), arts. 1, 12(6), 13(5), 17(10), 18(5), 21(4), 22(5), 27(4), 28(6), 29(7), 35(3) (with arts. 17(9), 22(6), 27(5), 28(7), 29(8))Pt. 1 applied (11.3.2015) by The Dogger Bank Creyke Beck Offshore Wind Farm Order 2015 (S.I. 2015/318), arts. 1, 14(5), 18(10), 19(6), 21(4), 24(6), 25(4), 28(4)(b), 29(6), 30(7), 36(4), 38(3) (with arts. 8(5), 18(9), 25(5), 28(5), 29(7), 30(8), 40, 41, Sch. 12 Pt. 1 paras. 4, 9(2), 10, Sch. 12 Pt. 2 paras. 4(2)(3), 19, Sch. 12 Pt. 3 para. 3, Sch. 12 Pt. 4 paras. 3, 4, 16)Pt. 1 applied (1.4.2015) by The Knottingley Power Plant Order 2015 (S.I. 2015/680), arts. 1, 11(4), 16(5), 21(8), 22(4), 26(4), 27(6), 28(7), 34(3) (with arts. 7(6), 22(5)(7), 27(7), 28(8), 31, Sch. 8 para. 10)Pt. 1 applied (21.4.2015) by The Crossrail (Plumstead Sidings) Order 2015 (S.I. 2015/781), arts. 1, 6(3), 7(5), 21(3)Pt. 1 applied (21.4.2015) by The Network Rail (Ordsall Chord) Order 2015 (S.I. 2015/780), arts. 1, 11(4), 12(6), 18(10), 19(5), 20(3), 26(4)(5), 27(6), 28(7), 32(5), 35(3) (with art. 36(2))Pt. 1 applied (9.6.2015) by The White Moss Landfill Order 2015 (S.I. 2015/1317), arts. 1, 10(5), 11(3), 16(3) (with arts. 5, 16(4)(5))Pt. 1 excluded (9.6.2015) by The White Moss Landfill Order 2015 (S.I. 2015/1317), arts. 1, 15(2) (with art. 5)Pt. 1 applied (23.6.2015) by The Norfolk County Council (Norwich Northern Distributor Road (A1067 to A47(T))) Order 2015 (S.I. 2015/1347), arts. 1, 12(6), 14(6), 18(10), 19(5), 24(5), 28(4)(5), 29(6), 30(7), 35(3), 36(5) (with art. 24(6))Pt. 1 modified (30.6.2015) by The Swansea Bay Tidal Generating Station Order 2015 (S.I. 2015/1386), arts. 1, 41(3) (with arts. 51, 53)Pt. 1 applied (30.6.2015) by The Swansea Bay Tidal Generating Station Order 2015 (S.I. 2015/1386), arts. 1, 10(5), 14(10), 15(5), 24(3), 25(5), 26(4), 28(4), 32(4)(5), 33(6), 34(7), 36(2) (with arts. 51, 53))Pt. 1 modified (7.8.2015) by The Preesall Underground Gas Storage Facility Order 2015 (S.I. 2015/1561), arts. 1, 23(6) (with arts. 23(7), 44)Pt. 1 applied (7.8.2015) by The Preesall Underground Gas Storage Facility Order 2015 (S.I. 2015/1561), arts. 1, 16(10), 17(5), 18(3), 19(4), 24(7), 32(4), 33(4), 37(3) (with arts. 20, 23, 32(5), 33(5), 44)Pt. 1 modified (14.8.2015) by The Hirwaun Generating Station Order 2015 (S.I. 2015/1574), arts. 1, 27(7) (with arts. 27(8), 30)Pt. 1 applied (14.8.2015) by The Hirwaun Generating Station Order 2015 (S.I. 2015/1574), arts. 1, 15(5), 21(5), 25(4), 26(6), 31(3) (with arts. 21(6), 25(5), 26(11), 30)Pt. 1 modified (14.8.2015) by The Progress Power (Gas Fired Power Station) Order 2015 (S.I. 2015/1570), arts. 1, 27(6), 28(7), 32(3) (with art. 27(5))Pt. 1 applied (14.8.2015) by The Progress Power (Gas Fired Power Station) Order 2015 (S.I. 2015/1570), arts. 1, 16(5), 22(5), 26(4) (with arts. 22(6), 26(5))Pt. 1 applied (26.8.2015) by The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015 (S.I. 2015/1592), arts. 1, 15(5), 19(10), 20(6), 25(6), 28(4), 29(6), 30(7), 36(4), 38(3) (with arts. 8, 20(7), 24(2), 28(5), 29(7), 30(8), 35, 40, 41, Sch. 12 para. 2)Pt. 1 applied (30.9.2015) by The Network Rail (Blackthorn and Piddington) (Land Acquisition) Order 2015 (S.I. 2015/1684), arts. 1, 7(6), 11(5)Pt. 1 applied (19.11.2015) by The Ferrybridge Multifuel 2 Power Station Order 2015 (S.I. 2015/1832), arts. 1(2), 13(7), 14(4), 15(5)(6)Pt. 1 applied (with modifications) (16.12.2015) by The Network Rail (Tinsley Chord) Order 2015 (S.I. 2015/1876), arts. 1, 18(6) (with art. 24(2))Pt. 1 applied (16.12.2015) by The Network Rail (Tinsley Chord) Order 2015 (S.I. 2015/1876), arts. 1, 9(10), 10(5), 19(7), 23(5), 26(3) (with art. 23(6))Pt. 1 applied (12.1.2016) by The London Underground (Bank Station Capacity Upgrade) Order 2015 (S.I. 2015/2044), arts. 1, 12(5), 13(6), 18(10), 19(6), 25(3), 26(6), 30(4) (with art. 19(7))Pt. 1 applied (2.2.2016) by The East Midlands Gateway Rail Freight Interchange and Highway Order 2016 (S.I. 2016/17), arts. 1, 11(6), 13(4), 23(5), 30(4)(5), 31(6), 37(3) (with art. 32)Pt. 1 applied (9.2.2016) by The National Grid (Hinkley Point C Connection Project) Order 2016 (S.I. 2016/49), arts. 1, 13(6), 17(10), 18(5), 28(4), 29(8), 31(7), 39(5), 41(3), 42(4) (with arts. 21(2), 28(5), 29(9), 31(8), 32)Pt. 1 applied (18.2.2016) by The A19/A1058 Coast Road (Junction Improvement) Development Consent Order 2016 (S.I. 2016/73), arts. 1, 11(5), 12(5), 16(10), 17(5), 22(5), 26(4), 27(6), 28(7), 32(3) (with arts. 22(6), 26(5), 37)Pt. 1 applied (25.3.2016) by The Thorpe Marsh Gas Pipeline Order 2016 (S.I. 2016/297), arts. 1, 13(5), 18(6), 23(7), 24(4), 28(4), 29(7), 30(7), 37(3), 38(4) (with arts. 24(5), 28(5), 39)Pt. 1 applied (1.6.2016) by The A14 Cambridge to Huntingdon Improvement Scheme Development Consent Order 2016 (S.I. 2016/547), arts. 1, 13(6) , 14(5), 18(10), 19(5), 25(5), 29(4), 30(6), 31(7), 36(3), 37(4) (with arts. 4, 5(3))Pt. 1 applied (14.6.2016) by The Midland Metro (Birmingham City Centre Extension, etc.) (Land Acquisition and Variation) Order 2016 (S.I. 2016/545), arts. 1, 11(4), 16(10), 24(3), 18(5), 25(6), 26(7), 29(3) (with arts. 24(4)(5), 26(8), 29(4), 39)Pt. 1 applied (2.8.2016) by The Midland Metro (Wolverhampton City Centre Extension) Order 2016 (S.I. 2016/684), arts. 1, 12(6), 21(10), 22(5), 26(3), 32(3)(5), 33(6), 34(7) (with arts. 46, 47, Sch. 9 para. 4, Sch. 10 para. 12(2))Pt. 1 applied (2.8.2016) by The Meaford Gas Fired Generating Station Order 2016 (S.I. 2016/779), arts. 1, 23(4), 25(6), 29(3) (with art. 23(5))Pt. 1 applied (10.8.2016) by The York Potash Harbour Facilities Order 2016 (S.I. 2016/772), arts. 1, 15(10), 16(5), 24(6), 29(4), 30(6)(17) (with arts. 29(5), 35, 36)Pt. 1 applied (19.8.2016) by The North Wales Wind Farms Connection Order 2016 (S.I. 2016/818), arts. 1, 23(4), 26(4), 27(6), 28(7), 31(3) (with art. 23(5), 27(7)(8)(11), 28(7), 35)Pt. 1 applied (7.9.2016) by The Hornsea Two Offshore Wind Farm Order 2016 (S.I. 2016/844), arts. 1(2), 11(6), 16(10), 17(5), 19(8), 21(4), 25(4), 26(8), 27(7), 30(3), 31(4) (with arts. 21(5), 37, 38)Pt. 1 applied (15.9.2016) by The River Humber Gas Pipeline Replacement Order 2016 (S.I. 2016/853), arts. 1, 14(5), 19(6), 23(5), 27(6), 28(7), 36(4), 41(7) (with art. 43)Pt. 1 applied (23.9.2016) by The M4 Motorway (Junctions 3 to 12) (Smart Motorway) Development Consent Order 2016 (S.I. 2016/863), arts. 1, 13(4), 14(7), 16(4), 18(10), 19(5), 23(5), 27(4), 28(6), 29(7), 35(3), 36(4)Pt. 1 applied (27.9.2016) by The Triton Knoll Electrical System Order 2016 (S.I. 2016/880), arts. 1(2), 9(6), 13(6), 19(5), 22(4), 24(7), 25(7), 34(6) (with arts. 19(6), 24(8), 25(8), 39, 40, Sch. 8 para. 19)Pt. 1 applied (24.11.2016) by The Transport for Greater Manchester (Light Rapid Transit System) (Trafford Park Extension) Order 2016 (S.I. 2016/1035), arts. 1, 13(6), 14(6), 20(9), 22(10), 24(5), 32(3), 33(6), 34(7) (with arts. 32(4)(5), 43, 44)Pt. 1 applied (23.2.2017) by High Speed Rail (London - West Midlands) Act 2017 (c. 7), ss. 9(8), 16(4), 55(6)(a), 70(1), Sch. 16 para. 9(5)Pt. 1 applied (18.3.2017) by The North London Heat and Power Generating Station Order 2017 (S.I. 2017/215), arts. 1, 13(5), 17(10), 18(5), 19(3), 22(4), 24(3), 25(3), 26(8), 27(6), 32(3) (with arts. 24(4), 25(4))Pt. 1 applied (29.3.2017) by The Glyn Rhonwy Pumped Storage Generating Station Order 2017 (S.I. 2017/330), arts. 1, 11(3), 13(6), 18(5), 22(6), 23(5) (with arts. 25, 31)Pt. 1 applied (5.4.2017) by The Keuper Underground Gas Storage Facility Order 2017 (S.I. 2017/433), arts. 1, 13(8), 17(10), 18(5), 19, 22(4), 27(6), 28(7), 30(4) (with arts. 27(11), 30(5))Pt. 1 modified (5.4.2017) by The Keuper Underground Gas Storage Facility Order 2017 (S.I. 2017/433), arts. 1, 31(4), 33(3)Pt. 1 applied (8.8.2017) by The Wrexham Gas Fired Generating Station Order 2017 (S.I. 2017/766), arts. 1, 16(6), 24(5), 25(5), 26(6), 27(7), 31(3) (with arts. 24(6), 25(7), 27(8))Pt. 1 applied (24.8.2017) by The National Grid (Richborough Connection Project) Development Consent Order 2017 (S.I. 2017/817), arts. 1, 13(6), 17(10), 18(5), 27(4)(5), 29(8), 30(7), 28(8), 38(4) (with arts. 17(9), 22, 28(9), 29(12))Pt. 1 applied (29.8.2017) by The East Anglia THREE Offshore Wind Farm Order 2017 (S.I. 2017/826), arts. 1, 18(4), 22(4), 23(6), 24(7), 31(3) (with arts. 5(9), 18(5), 24(8), 36, 37, Sch. 8 para. 34)Pt. 1 applied (5.9.2017) by The London Overground (Barking Riverside Extension) Order 2017 (S.I. 2017/830), arts. 1, 9(4), 10(6), 13(3), 16(10), 18(5), 19(3), 28(6), 29(7), 32(4) (with art. 32(5), Sch. 8 para. 20)Pt. 1 applied (with modifications) (5.9.2017) by The London Overground (Barking Riverside Extension) Order 2017 (S.I. 2017/830), arts. 1, 27(3)(5) (with Sch. 8 para. 20)Pt. 1 applied (15.11.2017) by The Network Rail (Summerway Overbridge) Order 2017 (S.I. 2017/1027), arts. 1, 3(2), 4(6), 6(2) (with art. 4(7))Pt. 1 applied (8.12.2017) by The Network Rail (Closure of Abbots Ripton Level Crossing) Order 2017 (S.I. 2017/1074), arts. 1, 5(4), 7(10), 9(6), 11(3) (with arts. 5, 9(7))Pt. 1 applied (19.12.2017) by The Network Rail (Buxton Sidings Extension) Order 2017 (S.I. 2017/1150), arts. 1, 9(4)(5), 10(6), 16(10), 17(5), 23(6), 24(7), 27(5), 31(3) (with arts. 17(6), 24(8), 27(6), 32(2))Pt. 1 applied (22.12.2017) by The M20 Junction 10a Development Consent Order 2017 (S.I. 2017/1202), arts. 1, 14(5), 15(6), 19(10), 20(5), 26(5), 30(4), 31(6), 32(7), 38(3), 39(4) (with arts. 4, 18(9), 30(5), 31(7), 32(8), 37)Pt. 1 applied (2.1.2018) by The Boston Barrier Order 2017 (S.I. 2017/1329), arts. 1, 12(6), 15(3), 21(10), 23(5), 24(3), 37(3), 38(6), 39(7), 42(4) (with arts. 37(5), 39(8), 55-57, Sch. 8 para. 13)Pt. 1 applied (4.1.2018) by The Blackpool Tramway (Blackpool North Extension) Order 2017 (S.I. 2017/1214), arts. 1, 12(6), 18(7), 20(10), 23(5), 31(3), 32(6), 33(7), 35(4), 42(4) (with arts. 30(7)(5), 42(3), 58, 59)Pt. 1 applied (18.4.2018) by The Network Rail (Hope Valley Capacity) Order 2018 (S.I. 2018/446), arts. 1, 9(6), 13(7), 15(10), 16(5), 23(3), 24(6), 25(7), 32(3) (with arts. 16(6), 23(5), 24(7)(8), 25(8), 33(2))Pt. 1 applied (31.5.2018) by The Silvertown Tunnel Order 2018 (S.I. 2018/574), arts. 1(2), 9(7), 10(5), 15(10), 13(3), 16(5), 18(3), 23(5), 28(4), 29(4)(9), 30(4)(10) (with arts. 28(5), 29(10), 30(11))Pt. 1 applied (4.6.2018) by The Network Rail (Kings Mill No. 1 Level Crossing) (Land Acquisition and Closure) Order 2018 (S.I. 2018/571), arts. 1, 3(4), 9(6), 10(5), 13(4)(5) (with arts. 3(5), 9(6), 10(6), 13(7))Pt. 1 applied (28.6.2018) by The High Speed Rail (London West Midlands) (Greatmoor Railway Sidings Etc.) Order 2018 (S.I. 2018/693), arts. 1, 5(7), 6(5), 14(3)Pt. 1 applied (24.8.2018) by The Network Rail (Werrington Grade Separation) Order 2018 (S.I. 2018/923), arts. 1, 10(6), 11(6), 17(15), 24(6), 23(4), 25(7), 27(5), 30(3) (with arts. 17(16), 23(5), 24(7), 25(8), 27(6), 31(2))Pt. 1 applied (26.9.2018) by The Network Rail (Felixstowe Branch Line Improvements Level Crossings Closure) Order 2018 (S.I. 2018/937), arts. 1, 5(7), 7(3), 8(15), 9(6), 14(6), 17(3) (with arts. 5(8), 8(17), 14(7), 17(5))Pt. 1 applied (3.10.2018) by The A19/A184 Testos Junction Alteration Development Consent Order 2018 (S.I. 2018/994), arts. 1, 12(5), 13(6), 18(10), 19(5), 24(5), 28(4), 29(6), 30(7), 34(3), 35(4) (with arts. 3(3), 5, 22)Pt. 1 applied (12.10.2018) by The Eggborough Gas Fired Generating Station Order 2018 (S.I. 2018/1020), arts. 1, 11(5), 15(5), 21(5), 25(4)(5), 26(6)(7), 27(7)(8), 31(3), 32(10) (with arts. 6, 21(6), 42)Pt. 1 applied (13.3.2019) by The Port of Tilbury (Expansion) Order 2019 (S.I. 2019/359), arts. 1, 12(7), 13(5), 16(3), 19(10), 20(5), 21(3), 27(4)(5), 29(4)(5), 32(6), 33(7) (with arts. 32(7), 33(8), 55, 56)Pt. 1 applied (3.4.2019) by The Millbrook Gas Fired Generating Station Order 2019 (S.I. 2019/578), arts. 1, 11(6), 12(4), 17(5), 22(5), 26(4), 27(6), 28(7), 32(4) (with arts. 21(6), 26(5), 27(7), 28(8), 30)Pt. 1 applied (7.5.2019) by The Midland Metro (Birmingham City Centre Extension, etc.) (Edgbaston Extension Land Acquisition) Order 2019 (S.I. 2019/882), arts. 1, 8(6), 9(7), 10(3) (with art. 18)Pt. 1 applied (10.10.2019) by The Abergelli Power Gas Fired Generating Station Order 2019 (S.I. 2019/1268), arts. 1, 11(6), 12(5), 17(5), 23(5), 27(4), 28(6), 29(7), 34(4)Pt. 1 applied (25.10.2019) by The Drax Power (Generating Stations) Order 2019 (S.I. 2019/1315), arts. 1, 12(5), 13(4), 17(5), 23(5), 27(4), 28(7), 29(7), 34(3), 35(10) (with arts. 23(6), 27(5), 28(8), 29(8), 35(9))Pt. 1 applied (30.10.2019) by The Northampton Gateway Rail Freight Interchange Order 2019 (S.I. 2019/1358), arts. 1, 10(4), 11(4), 22(5), 24(3), 25(5), 26(5), 33(4), 34(6), 35(7), 42(3) (with arts. 26(6), 33(5), 34(7), 35(8), Sch. 13 Pt. 1 para. 19)Pt. 1 modified (30.10.2019) by The Northampton Gateway Rail Freight Interchange Order 2019 (S.I. 2019/1358), art. 1, Sch. 12 para. 2 (with Sch. 13 Pt. 1 para. 19)Pt. 1 applied (25.2.2020) by The Network Rail (East West Rail) (Bicester to Bedford Improvements) Order 2020 (S.I. 2020/114), arts. 1, 8(4), 9(7), 10(3), 13(6), 14(6), 20(10), 21(15), 27(4) (with arts. 27(5), 37(2))Pt. 1 applied (27.2.2020) by The A30 Chiverton to Carland Cross Development Consent Order 2020 (S.I. 2020/121), arts. 1, 15(5), 16(6), 21(10), 22(5), 28(5), 32(4), 33(6), 34(7), 39(3), 40(2)(b) (with arts. 3(1), 32(5), 33(7), 34(8))Pt. 1 applied (4.3.2020) by The Midland Metro (Birmingham Eastside Extension) Order 2020 (S.I. 2020/141), arts. 1, 22(10), 23(9), 33(4), 34(6), 35(7) (with arts. 47, 48, Sch. 10 para. 19)Pt. 1 applied (14.4.2020) by The Reinforcement to the North Shropshire Electricity Distribution Network Order 2020 (S.I. 2020/325), arts. 1, 11(5), 27(7), 31(3) (with arts. 7, 11(6), 27(8))Pt. 1 applied (14.4.2020) by The Reinforcement to the North Shropshire Electricity Distribution Network Order 2020 (S.I. 2020/325), arts. 4, 21(3) (with arts. 7, 21(4)(5))Pt. 1 applied (30.4.2020) by The A585 Windy Harbour to Skippool Highway Development Consent Order 2020 (S.I. 2020/402), arts. 1, 12(5), 13(6), 18(10), 19(5), 24(5), 28(4), 29(6), 30(7), 34(6), 37(4) (with arts. 5, 24(6), 28(5), 29(8), 30(8), 32, 44)Pt. 1 applied (1.5.2020) by The Riverside Energy Park Order 2020 (S.I. 2020/419), arts. 1, 13(6), 14(3), 19(6), 20(10), 21(3), 26(5), 30(4), 31(6), 32(7) (with arts. 7, 20(9), 26(6), 30(5), 31(7), 32(8), 34)Pt. 1 applied (21.5.2020) by The Lake Lothing (Lowestoft) Third Crossing Order 2020 (S.I. 2020/474), arts. 1, 11(5), 14(3), 16(11), 17(5), 18(3), 19(4), 28(4), 30(4), 33(7), 34(6)(8), 44(5) (with arts. 28(5), 30(5), 34(9), 33(8), 51, 56, 57)Pt. 1 applied (25.5.2020) by The West Midlands Rail Freight Interchange Order 2020 (S.I. 2020/511), arts. 1, 10(5), 11(4), 22(5), 24(3), 25(7), 26(5), 33(4), 34(6), 35(7), 41(3) (with arts. 10(6), 26(6), 33(5), 34(7), 35(8))Pt. 1 applied (11.6.2020) by The M42 Junction 6 Development Consent Order 2020 (S.I. 2020/528), arts. 1, 16(7), 17(7), 22(11), 23(5), 28(5), 32(4), 33(6), 34(9), 39(5) (with arts. 17(8), 28(6), 32(5), 33(8), 34(10), 37)Pt. 1 applied (18.6.2020) by The A63 (Castle Street Improvement, Hull) Development Consent Order 2020 (S.I. 2020/556), arts. 1, 12(5), 13(6), 18(11), 19(5), 24(5), 28(4), 29(6), 30(7), 35(4) (with arts. 5, 13(7), 18(10), 28(5), 29(8), 30(8), 44)Pt. 1 applied (19.6.2020) by The Cleve Hill Solar Park Order 2020 (S.I. 2020/547), arts. 1, 10(6), 14(10), 15(5), 23(4), 24(6), 25(7), 19(4), 32(3), 33(4) (with arts. 14(9), 19(5), 23(5), 24(7), 25(8), 37)Pt. 1 applied (22.7.2020) by The Norfolk Vanguard Offshore Wind Farm Order 2020 (S.I. 2020/706), arts. 1, 11(6), 16(6), 21(4), 25(4), 26(6), 27(8), 35(3), 39(5) (with arts. 21(5), 25(5), 26(7), 27(9), 41, 42, 43, Sch. 16 para. 66)Pt. 1 applied (6.8.2020) by The A19 Downhill Lane Junction Development Consent Order 2020 (S.I. 2020/746), arts. 1, 12(5), 13(6), 18(10), 19(5), 24(5), 28(4), 29(6), 31(7), 35(3) (with arts. 5, 18(9), 24(6), 28(5), 29(8), 31(8), 33)Pt. 1 applied (1.9.2020) by The Immingham Open Cycle Gas Turbine Order 2020 (S.I. 2020/847), arts. 1, 16(5), 22(5), 26(4), 27(7), 28(8), 32(3), 33(10) (with arts. 22(6), 26(5), 27(8), 28(9), 33(9), Sch. 9 para. 144)Pt. 1 applied (23.9.2020) by The Midland Metro (Wednesbury to Brierley Hill Land Acquisition) Order 2020 (S.I. 2020/1067), arts. 7(6), 8(7), 10(3) (with art. 11(2))Pt. 1 applied (15.10.2020) by The Great Yarmouth Third River Crossing Development Consent Order 2020 (S.I. 2020/1075), arts. 1, 14(6), 15(5), 21(11), 22(5), 29(5), 35(5)(7), 36(6)(8), 49(4), 53(3), 54(4) (with arts. 29(6), 35(8), 36(9))Pt. 1 applied (29.10.2020) by The Southampton to London Pipeline Development Consent Order 2020 (S.I. 2020/1099), arts. 1, 13(7), 14(3), 19(10)(11), 20(7), 25(5), 29(4), 30(6), 31(8), 42(5), 43(4) (with arts. 19(9), 25(6), 29(5), 30(8), 31(9), 32, Sch. 9 para. 36)Pt. 1 applied (11.11.2020) by The West Burton C (Gas Fired Generating Station) Order 2020 (S.I. 2020/1148), arts. 1, 9(5), 14(5)
- C362Act applied (with modifications) (4.3.2026) by The Outer Dowsing Offshore Wind Farm Order 2026 (S.I. 2026/138), art. 1(2), Sch. 8 paras. 1, 3 (with arts. 42, 43, Sch. 18)
- F107S. 19(4) inserted (31.1.2025) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 189(5)(b), 255(7) (with s. 247); S.I. 2024/92, reg. 5 (with reg. 6(3)-(5))
- F108S. 17 substituted (6.4.2012) by Localism Act 2011 (c. 20), ss. 232(3), 240(2) (with s. 232(8)); S.I. 2012/628, art. 8(d) (with arts. 9, 12, 13, 16, 18-20) (as amended (3.8.2012) by S.I. 2012/2029, arts. 2, 4)
- F109S. 18 substituted (6.4.2012) by Localism Act 2011 (c. 20), ss. 232(3), 240(2) (with s. 232(8)); S.I. 2012/628, art. 8(d) (with arts. 9, 12, 13, 16, 18-20) (as amended (3.8.2012) by S.I. 2012/2029, arts. 2, 4)
- C363S. 5(2)-(4) applied by 1954 c. 56, s. 34C(3) (as inserted (7.4.2026) by Product Security and Telecommunications Infrastructure Act 2022 (c. 46), ss. 63, 79(2); S.I. 2025/1326, reg. 2(c) (with regs. 3-5))